Q2 FY27 earnings and concall highlights

Price as of 16 Nov 2026
1,894.40−7.14%

Q2 FY27 earnings call · Guided by management

Call held 6 Nov 2026 · Read the filing on NSEFiling

15–20​%Revenue CAGR · medium-termSeetharaman · p. 7
20​%O&M share of revenue · O&M · medium-termSeetharaman · p. 7
13–15​%EBITDA margin · medium-termSeetharaman · p. 7
15​%ROE · medium-termSeetharaman · p. 7
M.Cap
₹11,838Cr
P/E
27.4×
1Y return
+34.40%
From 52W high
−18.3%

Highlights are read by AI from the company's filing and can contain mistakes. Check the source page linked to each line.

Share price

Results Q2 FY27, as filed · consolidated · ₹ Cr

Q2 FY27Q2 FY26YoYQ1 FY27QoQ
Revenue1,000835+19.9%887+12.8%
EBITDA12489+39.2%80+56.4%
EBITDA margin12.4%10.7%+173 bps9.0%+347 bps
One-off items—1———
PBTProfit before tax136111+22.7%113+20.7%
Net profit10585+23.5%89+16.9%
EPS (₹)17.3513.45+29.0%14.16+22.5%

From the company's own results filing on NSE. Net profit is the owners' share. Growth and the dotted lines are worked out from the filed figures. In Q2 FY27 the filing tags the owners' profit as ₹110 Cr against its own period profit; the period profit less minority interest is shown.

Guidance

Revenue growth · long term15-20%keptMedium-term revenue CAGR objective of 15%-20% reiterated
EBITDA margin · long term13-15%keptMedium-term EBITDA margin objective of 13%-15% reiterated
Return on equity · long term15%keptMedium-term ROE objective above 15% reiterated

Management hopes for a large order intake over the next 12-18 months

Rajiv Mittal · Chairman and Managing Director · p. 10
“We are very hopeful the next 12-18 months is going to be a bumper order intake for us.”

More figures from the call

Company · Guidance
20​%ROCE · medium-term
“We reiterate our medium-term objectives: revenue CAGR of 15%-20%, EBITDA in the 13%-15% band, ROCE above 20%, ROE above 15%, and O&M progressing to 20% of revenue, and a sustained positive net cash position.”
Skandaprasad Seetharaman · Group Chief Financial Officerp. 7
Company · Guidance
20–30​%EP share of orders
“but on an average, we would like to see at least anywhere between 20% to 30% of our orders coming from EP.”
Skandaprasad Seetharaman · Group Chief Financial Officer · Q&Ap. 11
India industrial · Order book
201​MLDDesalination plant capacity
“securing a Mega order for desalination plant in Jamnagar with a capacity of approximately 201 million liters per day, expandable to approximately 302 million liters per day, and also a remineralization plant of approximately 72 million liters per day.”
Rajiv Mittal · Chairman and Managing Directorp. 4
India · Other
90​%Concreting completed
“We have done about 90% concreting, poured overall almost 1 lakh cubic meter of concreting.”
Bhupesh Chowdaryp. 5
India · Demand
400​MLDAnnounced desalination plant size
“a very large desalination plant, similar size to what we are executing in Perur, a 400 MLD on the North Chennai has been announced.”
Rajiv Mittal · Chairman and Managing Director · Q&Ap. 10
Company · Order book
80​%Share of order intake · first quarter
“Our focus on taking EP projects continues to remain, and this is clearly demonstrated in just these two, which will account for almost 80% of the first quarter order intake.”
Skandaprasad Seetharaman · Group Chief Financial Officer · Q&Ap. 10

In short

  1. 01Order book at a record Rs 20,207 crore after H1 FY27 order intake of Rs 5,200 crore.
  2. 02Medium-term targets reiterated: revenue CAGR 15%-20%, EBITDA margin 13%-15%, ROCE above 20%, ROE above 15%.
  3. 03H1 FY27 revenue Rs 1,887 crore, up 20.3%; PAT up almost 30% to Rs 195 crore.
  4. 04Net cash excluding HAM over Rs 1,100 crore; Rs 1,036 crore including HAM.
  5. 05Middle East conflict causing large shipment delays and commodity price pressure; no impact on results so far.
  6. 06Management hopes the next 12-18 months bring a large order intake; bidding at a peak.
  7. 07Middle East new-project awards slowed; Saudi projects where WABAG is preferred bidder expected to move in about a quarter.
  8. 08Al Haer plant commissioning targeted for Q4 FY27; Bangladesh project may see about six months of delay.

Order book

Order book at Rs 20,207 crore at end of H1 FY27; H1 order intake Rs 5,200 crore

Rajiv Mittal · Chairman and Managing Director · p. 5
“Our order book reaches a lifetime high of INR 20,207 crore at the end of H1 FY2027, supported by order intake of INR 5,200 crore during the first half.”

O&M: O&M order backlog at Rs 6,500 crore

Skandaprasad Seetharaman · Group Chief Financial Officer · p. 8
“O&M is building steadily towards the 20% objective on the back of a historic high order backlog in O&M of INR 6,500 crores.”

Middle East: Kuwait 60 MIGD (about 272 MLD) seawater desalination contract signed with HEISCO

Rajiv Mittal · Chairman and Managing Director · p. 4
“During H1, we signed and commenced the contract with the Ministry of Electricity, Water and Renewable Energy, Kuwait in partnership with HEISCO for a 60 MIGD or approximately 272 million liters per day of seawater reverse osmosis desalination facility.”

Middle East: Kuwait project about USD 400 million, signed with consortium partner last quarter

Rajiv Mittal · Chairman and Managing Director · p. 9
“we just signed in last quarter a large, almost about USD 400 million project with our consortium partner or a joint venture partner.”

India industrial: Repeat Medium order from Reliance for effluent treatment plant at Jamnagar

Rajiv Mittal · Chairman and Managing Director · p. 4
“In September, we had also received a repeat Medium order from Reliance Industries Limited for an effluent treatment plant at Dhirubhai Ambani Green Energy Giga Complex in Jamnagar.”

Segments

H1 revenue: international 54%, India 46%; EPC 82%, O&M 18%

Skandaprasad Seetharaman · Group Chief Financial Officer · p. 7
“international markets contributing 54% of H1 revenue and India 46%. By business, EPC accounted for 82% and O&M for 18%.”

Europe: Activity picking up in Europe cluster; two contracts won there

Rajiv Mittal · Chairman and Managing Director · p. 9
“In the last couple of quarters, we have seen some activities in the European cluster, and we have also got two contracts in European cluster.”

Sunrise sectors: Sunrise-sector orders (data centres, solar, semiconductors) will be much smaller in size

Rajiv Mittal · Chairman and Managing Director · Q&A · p. 15
“These order sizes are never going to be INR 5,000 crores or INR 1,000 crores, a single order. They are going to be much smaller.”

Sunrise sectors: Separate team for sunrise-sector orders with 12-15 month gestation

Rajiv Mittal · Chairman and Managing Director · Q&A · p. 16
“So we need to have a specialized team who focuses on it and also executes this order because this gestation period of these orders are very small, generally 12-15 months.”

Demand

Middle East: Some delay expected in Middle East order conversion as governments await investment strategy

Rajiv Mittal · Chairman and Managing Director · Q&A · p. 9
“I think to some extent it is a fair assumption that there will be some delay because the governments are also waiting for the investment strategy, what they will have, what they will put in which basket.”

Saudi Arabia: Saudi slow, but preferred-bidder projects expected to move in about a quarter

Rajiv Mittal · Chairman and Managing Director · p. 9
“Yes, Saudi has been a little slow and a little cautious, but we again understand some of the projects where we were a preferred bidder, that is also started moving. So we expect in next quarter or so, we should have that also moving ahead.”

Bidding activity described as at a peak

Rajiv Mittal · Chairman and Managing Director · p. 9
“So overall, we are at a peak in terms of the bidding activities. We are very bullish about future.”

India: Enquiries from Gujarat, Maharashtra, Andhra Pradesh and Tamil Nadu

Bhupesh Chowdary · p. 14
“we also see a lot of inquiries coming in from Gujarat, Maharashtra, and also Andhra Pradesh and Tamil Nadu, from the desalination to the sewage treatment plants, from the municipality and industrial zones part of it.”

Middle East: In Middle East PPP projects, WABAG works with developers as EPC player

Bhupesh Chowdary · Q&A · p. 11
“We are basically going with them as part of an EPC player.”

Margins and costs

H1 EBITDA up about 21% to Rs 261 crore; PAT up almost 30% to Rs 195 crore; PAT margin 10.3%

Skandaprasad Seetharaman · Group Chief Financial Officer · p. 7
“EBITDA grew by about 21% to INR261 crores at a margin of almost 14%. PAT grew faster, up by almost 30% to INR195 crores, and PAT margin expanded to 10.3% as against 9.6% in the same period last year.”

No one-off in Q2 gross margin; described as structural improvement

Skandaprasad Seetharaman · Group Chief Financial Officer · Q&A · p. 12
“Also, it goes by the project mix, the phase of the project. There is no one-off. It is a structural improvement that is there.”

Margin guidance includes commodity inflation; contracts pass it through by formula

Skandaprasad Seetharaman · Group Chief Financial Officer · Q&A · p. 12
“Yes. We have contracts which clearly have this pass-through to the customer through the formula, and that is also included here.”

Indian contracts use escalation formula; international commodity exposure hedged

Rajiv Mittal · Chairman and Managing Director · p. 13
“As Skanda said, most of the Indian contracts, we go with the escalation formula. Internationally, we immediately hedge.”

Q2 employee expense had no one-off; reflects increments and Wage Code impact

Skandaprasad Seetharaman · Group Chief Financial Officer · Q&A · p. 16
“Employee expenses, there is no one-off. This is in line because we give the increments in this quarter.”

Debt and working capital

Net cash excluding HAM over Rs 1,100 crore vs Rs 950 crore at end FY2026; Rs 1,036 crore including HAM

Skandaprasad Seetharaman · Group Chief Financial Officer · p. 7
“Turning to the balance sheet, net cash excluding HAM reached an all-time high of over INR 1,100 crores as compared to INR 950 crores at the end of FY2026. Including HAM, net cash stood at INR 1,036 crores.”

H1 operating cash flow Rs 225 crore; net working capital 101 days vs 104 days in March 2026

Skandaprasad Seetharaman · Group Chief Financial Officer · p. 7
“Consolidated operating cash flow for H1 was INR 225 crores, over 1.1x our PAT for the same period. Net working capital also improved to 101 days from 104 days as of March 2026.”

Letters of credit on some projects; no payment risk seen beyond a few weeks' delay

Rajiv Mittal · Chairman and Managing Director · p. 13
“And some of the projects, we even ask for letter of credit. So, from that point of view, we do not see a risk of payment or much delay of payment. There can be a few weeks or a month of delay, but that's okay.”

SAARC: Bangladesh project moving steadily; payments received on time

Rajiv Mittal · Chairman and Managing Director · Q&A · p. 14
“So the project is moving. It could move little faster, but it is moving steadily, and we are receiving our payments on time.”

Management

Succession planning uses homegrown and lateral talent

Rajiv Mittal · Chairman and Managing Director · Q&A · p. 18
“It's a combination of homegrown talent plus a lateral talent which we are bringing in to make sure we have a backup for this succession planning available.”

Promoter's son Rohan Mittal handles Middle East, GCC and Africa region

Rajiv Mittal · Chairman and Managing Director · Q&A · p. 18
“My son, Rohan Mittal, has been into the business for last nine years. He is handling the Middle East, GCC, and Africa region, and he's doing well.”

Rohan Mittal expected to take up a position in the company in coming years

Rajiv Mittal · Chairman and Managing Director · Q&A · p. 18
“He's being groomed by the seniors. I'm sure he will definitely grow to take up some position in the Company in the coming years.”

Risks

Middle East: Middle East disturbance causing commodity price pressure and huge shipment delays

Rajiv Mittal · Chairman and Managing Director · Q&A · p. 8
“But what we are facing, other than the commodity price pressures, is a huge delay in shipments.”

Middle East: New strategy for delivering equipment needed if situation does not improve in 3-6 months

Rajiv Mittal · Chairman and Managing Director · Q&A · p. 8
“As our new projects will start, we have to find a strategy if by that, in next three to six months, if the situation does not improve, we will have to find a strategy of delivering the equipment to site.”

Indosol has 900 of 1,000 acres; balance expected in about a quarter, then mega project starts

Rajiv Mittal · Chairman and Managing Director · Q&A · p. 12
“So - I think out of 1,000 acres, they have already secured 900 acres, another 100 acres which they should get pretty fast. So one would expect that in a quarter from now, they should be able to get this balance 100, and then they will kickstart the mega project.”

SAARC: Bangladesh project may face about six months delay; no margin impact expected

6​months
Rajiv Mittal · Chairman and Managing Director · Q&A · p. 14
“Yes, because of the disturbances and change of government, change of bureaucrats, there is some delay, but that is not going to affect our margin, other than there will be maybe six months of delay in the project.”

Only projects with payment security are taken

Rajiv Mittal · Chairman and Managing Director · p. 13
“We don't take projects which does not give us a payment security.”

Other

Q2 revenue crossed Rs 1,000 crore and PAT crossed Rs 100 crore

Skandaprasad Seetharaman · Group Chief Financial Officer · p. 6
“Our order book crossed INR 20,000 crores, H1 order intake crossed INR 5,000 crores, and net cash crossed INR 1,000 crores, all at record levels. In Q2, revenue crossed INR1,000 crores and PAT crossed INR 100 crores, the highest ever second quarter results that we have reported.”

Q2 consolidated revenue up 20% year-on-year; PAT up 23%

Skandaprasad Seetharaman · Group Chief Financial Officer · p. 6
“Taking the quarter first, consolidated revenue from operations was up by 20% year-over-year, and PAT was up by 23%.”

H1 consolidated revenue Rs 1,887 crore, up 20.3% year-on-year

Skandaprasad Seetharaman · Group Chief Financial Officer · p. 7
“For the half year, consolidated revenue from operations was INR1,887 crores, up 20.3% year-over-year.”

Standalone: Standalone H1 revenue up 19% to Rs 1,587 crore

Skandaprasad Seetharaman · Group Chief Financial Officer · p. 7
“At the standalone level, H1 revenue grew by 19% to INR 1,587 crores.”

ROE 16.3% in H1 vs 15.7% in March 2026; ROCE 20.5% vs 19.5%

Skandaprasad Seetharaman · Group Chief Financial Officer · p. 7
“Return on equity improved to 16.3% in H1 as against 15.7% in March 2026, and return on capital employed improved from 19.5% in March 2026 to 20.5% in H1 FY2027.”