Capital Goods · NSE: TITAGARH
TITAGARH RAIL SYSTEMS
Q2 FY27 earnings and concall highlights
Q2 FY27 earnings call · Guided by management
Call held 13 Nov 2026 · Read the filing on NSEFiling
- M.Cap
- ₹9,860Cr
- P/E
- 45.7×
- 1Y return
- −15.50%
- From 52W high
- −24.6%
Highlights are read by AI from the company's filing and can contain mistakes. Check the source page linked to each line.
Share price
Results Q2 FY27, as filed · consolidated · ₹ Cr
| Q2 FY27 | Q2 FY26 | YoY | Q1 FY27 | QoQ | |
|---|---|---|---|---|---|
| Revenue | 793 | 799 | -0.8% | 765 | +3.6% |
| EBITDA | 107 | 84 | +27.9% | 95 | +12.7% |
| EBITDA margin | 13.5% | 10.5% | +302 bps | 12.4% | +109 bps |
| PBTProfit before tax | 83 | 67 | +22.7% | 71 | +15.7% |
| Net profit | 63 | 37 | +70.8% | 53 | +20.2% |
| EPS (₹) | 4.62 | 2.73 | +69.2% | 3.84 | +20.3% |
From the company's own results filing on NSE. Net profit is the owners' share. Growth and the dotted lines are worked out from the filed figures.
Guidance
Vande Bharat: FY28 Vande Bharat numbers assume the contract schedule is adhered to
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 5
Vande Bharat: FY28 Vande Bharat numbers assume the contract schedule is adhered to
“So we are expecting that based on this schedule, is the numbers that we have projected for FY28 is considering this schedule which is there in the contract, which will be adhered to.”
metro: Company says it is confident of getting close to the car numbers in its roadmap
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 8
metro: Company says it is confident of getting close to the car numbers in its roadmap
“So that's, once again, we would not like to mention project by project, but overall, we are confident of being able to achieve close to the numbers that have been projected in the business, the outlook roadmap and the vision and roadmap.”
More figures from the call
“The most important of that being the number of metro cars invoiced during the quarter, which has gone up to 51, which means that we have been able to hit the run rate of 200 cars that was targeted for the year.”
“and thereafter, within two months or three months, somewhere around that, the second train has to be given. Then there will be a test period of around three months. After which the series production clearance should be accorded.”
“Right now, we have a clear visibility for three, four quarters of this year or maybe the next year as well.”
“But on the bigger picture, the plan of the railways to achieve the billion tons or to get to 40% market share is unchanged.”
In short
- 01Metro cars invoiced rose to 51 in the quarter, hitting the targeted 200-car yearly run rate.
- 02Order book, including JV share, is about Rs 28,600-28,700 crore; passenger rail is almost 70% of standalone order book.
- 03Management projects around 275 cars in FY28, and aims to get close to 200 metro cars in FY27.
- 04Wagon output to return to 1,000 a month by Q4 FY27 after the Indian Railways option order.
- 05First Vande Bharat prototype expected ready for testing late in Q4 FY27; delay not expected to hit margins.
- 06Mumbai Line 6 prototype expected in Q4 FY27, followed by Line 5; Pune aluminium coach production from Q1-Q2 FY28.
- 07No extra capex needed for propulsion; current metro contracts to be executed by FY28 end.
Capex
propulsion: Most propulsion capex already invested; no need to raise capex spend
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 6
propulsion: Most propulsion capex already invested; no need to raise capex spend
“We have already invested most of the capex. Whatever last we had announced for the capex plan, we are very well within the same number as of now. We do not need to enhance the capex spend for this current propulsion projects.”
Pune Metro: Most equipment acquired to make aluminium flat packs in India instead of importing from Italy
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 8
Pune Metro: Most equipment acquired to make aluminium flat packs in India instead of importing from Italy
“Earlier, we used to import the flat packs, the sub-assemblies from Italy, from our associate in Firema. But now we have already acquired most of the equipments to produce those flat packs in India.”
Capacity
mainline: Separate mainline facility for Vande Bharat is set up and can reach targeted production
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 4
mainline: Separate mainline facility for Vande Bharat is set up and can reach targeted production
“The facility has already been set up, and it is capable of achieving the targeted production once the first prototype is tested.”
metro: Production capacity is fungible between projects
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 8
metro: Production capacity is fungible between projects
“The production facility or the production capability capacity is fungible between different projects.”
aluminium coaches: Aluminium production bay under construction; first Indian-made coach expected Q1-Q2 FY28
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 8
aluminium coaches: Aluminium production bay under construction; first Indian-made coach expected Q1-Q2 FY28
“The new production area of the production bay for the aluminum is under construction. We are expecting that we will start the production of the first aluminum coach completely made in India in Q1 of FY28, by June or July, Q1, Q2 of FY28.”
wheels: Own wheel capacity in JV with Ramkrishna Forgings expected in full swing by next shortage
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 11
wheels: Own wheel capacity in JV with Ramkrishna Forgings expected in full swing by next shortage
“by the time the next round of this criticality comes in, our own capacity will be on full swing in the joint venture between us and Ramkrishna Forgings.”
Order book
Order book including JV share at about Rs 28,600 to 28,700 crore
Umesh Chowdhary · Vice Chairman and Managing Director · p. 2
Order book including JV share at about Rs 28,600 to 28,700 crore
“Overall order book of the company, including its share of the joint ventures, has gone up to about INR28,600 crores to INR28,700 crores.”
passenger rail system: Passenger rail is almost 70% of the standalone order book
Umesh Chowdhary · Vice Chairman and Managing Director · p. 2
passenger rail system: Passenger rail is almost 70% of the standalone order book
“In terms of the order book, the standalone order book, the passenger rail system is almost 70% of the order book.”
Pune Metro: Pune option quantity is for 12 aluminium trains
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 8
Pune Metro: Pune option quantity is for 12 aluminium trains
“The option quantity that we have got for Pune is for 12 trains for aluminum.”
Vande Bharat: Vande Bharat deliveries to continue four to five years; roadmap capacity pretty booked
4–5yearsUmesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 9
Vande Bharat: Vande Bharat deliveries to continue four to five years; roadmap capacity pretty booked
4–5years“The delivery is going to continue for another four, five years. If you see the capacity that we have given in our roadmap, it's pretty booked.”
Vande Bharat: Vande Bharat order is for 1,280 cars plus a 30% option in the contract
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 9
Vande Bharat: Vande Bharat order is for 1,280 cars plus a 30% option in the contract
“because the total order we have is for 1,280 cars, plus there is a 30% option that exists in the contract itself.”
Segments
PRS: Passenger rail had its highest quarterly revenue, now about 30%+ of company revenue
Umesh Chowdhary · Vice Chairman and Managing Director · p. 2
PRS: Passenger rail had its highest quarterly revenue, now about 30%+ of company revenue
“this has been the highest quarterly revenue for the PRS, which now constitutes to about 30%+ of the overall revenue of the company.”
Vande Bharat: Propulsion for current 1,280-car Vande Bharat contract will come from BHEL
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 5
Vande Bharat: Propulsion for current 1,280-car Vande Bharat contract will come from BHEL
“So this current contract which we have for 1,280 coaches or cars, plus if there is an option for that, the propulsion will come from BHEL.”
high speed: High speed is a mid to long term target, on an aluminium basis
Umesh Chowdhary · Vice Chairman and Managing Director · p. 9
high speed: High speed is a mid to long term target, on an aluminium basis
“Also, the high speed ultimately is going to be our target, and that is something which we would definitely be targeting in the mid to long term, and that has to be on an aluminum basis.”
traction motors: Traction motor supplies not large; company awaiting new traction motor orders
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 9
traction motors: Traction motor supplies not large; company awaiting new traction motor orders
“It's not been very large because we executed our orders for the traction motor, and now we are waiting for new traction motor orders to come our way.”
metro: Future contracts expected to have shorter gestation, avoiding a long production dip
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 10
metro: Future contracts expected to have shorter gestation, avoiding a long production dip
“The future contracts that will be coming up, the gestation period to start that should be shorter. We have that plan in place that we should not have a long period of dip for starting the production after completing the old projects.”
Demand
wagons: Indian Railways option quantity order eased short-term wagon demand uncertainty
Umesh Chowdhary · Vice Chairman and Managing Director · p. 2
wagons: Indian Railways option quantity order eased short-term wagon demand uncertainty
“the uncertainty or the short-term uncertainty that was prevailing for the wagon demand has been to a large extent addressed by way of this receipt of the option quantity of orders from the Indian Railways, which gives a certain amount of visibility for the immediate future.”
metro: Company is the only Indian private sector player established in metro, sees good road ahead
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 7
metro: Company is the only Indian private sector player established in metro, sees good road ahead
“Having entered into this segment and being the only private sector company, Indian private sector company in this segment, which has already established itself, we feel that there is a good road ahead for us.”
metro: Existing demand seen as sufficient for the company's business plan
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 8
metro: Existing demand seen as sufficient for the company's business plan
“We believe that the demand that exists is sufficient to cater to our business plan that we have given and in terms of the outlook in our presentation.”
aluminium coaches: Management sees aluminium coaches as the future of coach building in India
Umesh Chowdhary · Vice Chairman and Managing Director · p. 9
aluminium coaches: Management sees aluminium coaches as the future of coach building in India
“We believe that aluminum coaches is going to be the future of coach building in the country or coach requirement in the country.”
wagons: Overall wagon demand seen constant, though it can shift by a couple of quarters
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 10
wagons: Overall wagon demand seen constant, though it can shift by a couple of quarters
“The overall demand of the wagon on the whole is going to remain constant. This can be deferred by a couple of quarters here or a couple of quarters there.”
Margins and costs
propulsion: Own propulsion expected to improve EBITDA margins as it is a higher-margin business
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 6
propulsion: Own propulsion expected to improve EBITDA margins as it is a higher-margin business
“This will be extremely relevant for both having complete control on the passenger coach that we produce and also in improving our EBITDA margins, because propulsion is generally a higher-margin business”
Vande Bharat: Vande Bharat delay affects cash flow and overheads; direct costs covered by price variation
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 12
Vande Bharat: Vande Bharat delay affects cash flow and overheads; direct costs covered by price variation
“The delay impacts the cash flow and maybe the overheads, but as far as the direct cost is concerned, these are primarily contracts with price variation.”
Vande Bharat: Vande Bharat delay not expected to impact margin
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 12
Vande Bharat: Vande Bharat delay not expected to impact margin
“The short answer to your question for Vande Bharat is that it is not going to impact the margin.”
One or two quarters of delay do not impact margins on long-term projects
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 12
One or two quarters of delay do not impact margins on long-term projects
“In infrastructure projects, long-term projects of this nature, in any case, one or two quarters do not impact margins on the overall project itself.”
Acquisitions and new business
Vande Bharat: Joint venture agreement with BHEL for the Vande Bharat contract signed
Umesh Chowdhary · Vice Chairman and Managing Director · p. 2
Vande Bharat: Joint venture agreement with BHEL for the Vande Bharat contract signed
“Some of the other highlights are the joint venture agreement, which was on the cards as a part of the Vande Bharat contract, has been finally signed with BHEL.”
metro: Siemens MOU aims at cost-effective supply and access to global market via Siemens
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 5
metro: Siemens MOU aims at cost-effective supply and access to global market via Siemens
“But the idea is to be cost-effective so that they can also become globally competitive, and we can get access through the Siemens outreach to the global market.”
Siemens MOU is non-exclusive
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 5
Siemens MOU is non-exclusive
“This is non-exclusive, so it is not necessary that they will only go with us or we will only go with them.”
metro: Siemens MOU is for metro coaches, not wagons
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 13
metro: Siemens MOU is for metro coaches, not wagons
“As far as the MOU with Siemens is concerned, it is for metro coaches, it is not for wagons.”
metro: Siemens MOU is non-binding; aims to use the company's Indian production and engineering base
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 5
metro: Siemens MOU is non-binding; aims to use the company's Indian production and engineering base
“The idea of this MOU, which is a non-binding MOU, of course, but the idea is to use the cost-effective production facility, high-quality and cost-effective production facility that we have developed in India, and also the engineering capability that we have developed in India.”
Risks
Vande Bharat: Vande Bharat timelines adjusted for delays from 16 to 24 coach change and specification changes
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 3
Vande Bharat: Vande Bharat timelines adjusted for delays from 16 to 24 coach change and specification changes
“As we have already mentioned on the Vande Bharat, these are the adjusted timelines based on the delays that had happened on account of various factors, which is the 16 coach to 24 coach, there have been some change in specifications, etcetera.”
Delivery periods are usually rescheduled by customers with no penalties on the company
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 3
Delivery periods are usually rescheduled by customers with no penalties on the company
“But in most of the cases, these are acknowledged by the customer and the delivery periods are rescheduled with no penalties implied on us.”
Gulf War supply chain issues; government allowed rescheduling for chip-dependent products
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 6
Gulf War supply chain issues; government allowed rescheduling for chip-dependent products
“Plus, there have been certain challenges on supply chain because of the Gulf War, on account of which the Government of India themselves have allowed rescheduling of products or delivery period of products which require components like electronic chips, etcetera, etcetera.”
Mumbai Metro: Company does not expect delay beyond the period the government circular permits
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 6
Mumbai Metro: Company does not expect delay beyond the period the government circular permits
“We do not believe that we will be impacted beyond the period that the Government of India circular permits us”
Supply chain issues ongoing, but none seen as insurmountable
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 11
Supply chain issues ongoing, but none seen as insurmountable
“All I can say is as of this moment, we do not see any challenge which is unsurmountable.”
Other
Vande Bharat: First Vande Bharat prototype train expected ready for testing by Q4 FY27
Umesh Chowdhary · Vice Chairman and Managing Director · p. 2
Vande Bharat: First Vande Bharat prototype train expected ready for testing by Q4 FY27
“In terms of the Vande Bharat prototype train, the production is going on in full swing, and we are expecting the first train to be ready for testing by Q4 of the current financial year.”
Mumbai Metro: Mumbai Line 6 prototype expected Q4 FY27 or Q1 CY2027, followed by Line 5
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 6
Mumbai Metro: Mumbai Line 6 prototype expected Q4 FY27 or Q1 CY2027, followed by Line 5
“Both Line 5 and Line 6, we are expecting the prototype train for the Line 6 to be ready in the Q4 of the current financial year, or Q1 of the calendar year 2027. Which will be followed immediately with the prototype train of Line 5.”
Mumbai Metro: Car body production for Mumbai lines has begun
Umesh Chowdhary · Vice Chairman and Managing Director · p. 7
Mumbai Metro: Car body production for Mumbai lines has begun
“If I may also add here is that the production of the car body has already begun.”
metro: Metro trains need no extensive trials; series production starts right after
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 7
metro: Metro trains need no extensive trials; series production starts right after
“These do not have extensive trial like the Vande Bharat does. They are online tried out, then the series production starts immediately thereafter.”
Gujarat Metro: A couple of trains each delivered for Surat and Ahmedabad; rest in production
Umesh Chowdhary · Vice Chairman and Managing Director · Q&A · p. 8
Gujarat Metro: A couple of trains each delivered for Surat and Ahmedabad; rest in production
“We have already delivered a couple of trains each for Surat and Ahmedabad, and the production for the balance is also going on.”