Metals & Mining · NSE: SARDAEN
Sarda Energy & Minerals
Q2 FY27 earnings and concall highlights
Q2 FY27 earnings call · Guided by management
Call held 2 Nov 2026 · Read the filing on NSEFiling
- M.Cap
- ₹15,565Cr
- P/E
- 14.0×
- 1Y return
- −14.74%
- From 52W high
- −29.2%
Highlights are read by AI from the company's filing and can contain mistakes. Check the source page linked to each line.
Share price
Results Q2 FY27, as filed · consolidated · ₹ Cr
| Q2 FY27 | Q2 FY26 | YoY | Q1 FY27 | QoQ | |
|---|---|---|---|---|---|
| Revenue | 1,453 | 1,528 | -4.9% | 1,608 | -9.7% |
| EBITDA | 513 | 512 | +0.1% | 653 | -21.6% |
| EBITDA margin | 35.3% | 33.5% | +178 bps | 40.6% | -536 bps |
| PBTProfit before tax | 415 | 431 | -3.7% | 615 | -32.5% |
| Net profit | 306 | 323 | -5.3% | 458 | -33.2% |
| EPS (₹) | 8.68 | 9.17 | -5.3% | 13.00 | -33.2% |
From the company's own results filing on NSE. Net profit is the owners' share. Growth and the dotted lines are worked out from the filed figures.
Guidance
Thermal power: No thermal shutdown expected this quarter or next in normal course
Padam Jain · Q&A · p. 9
Thermal power: No thermal shutdown expected this quarter or next in normal course
“No, there is no need for any shutdown. Now, this quarter and next quarter, we won't require any shutdown in normal course.”
Thermal power: Thermal generation for the full year expected to exceed last year
Padam Jain · Q&A · p. 9
Thermal power: Thermal generation for the full year expected to exceed last year
“Yes, for the quarter, it has impacted, but for the year as a whole, we will exceed last year's generation.”
Thermal power: Environmental clearance for SKS expansion expected in this financial year
Pankaj Sarda · Managing Director · Q&A · p. 16
Thermal power: Environmental clearance for SKS expansion expected in this financial year
“Ma'am, as mentioned in my opening remarks as well, we have received TOR, (terms of reference) from the MoEF and we are expecting to get the Environmental Clearance in this financial year.”
More figures from the call
“The approval process for our 3 small hydropower projects in Chhattisgarh with an aggregate capacity of 74 megawatts is progressing as scheduled.”
“Our 50-megawatt captive solar project is expected to be commissioned in the next quarter, subject to resolution of right-of-way issues affecting the transmission line.”
“For our recently acquired 66-megawatt hydropower project in Arunachal Pradesh, most key statutory approvals are in place and critical land acquisition has been completed. Work on the approach road has commenced, and we remain confident of meeting the planned project timelines.”
“Operations are expected to commence in approximately 12 to 14 months. Once operational, the mine will strengthen backward integration, enhance raw material security, and improve cost competitiveness, supporting higher profitability in our ferro alloys business.”
“At our 600-megawatt thermal power plant, planned maintenance of one 300-megawatt unit was completed following a 47-day shutdown during the quarter.”
“So, that's why the raw material prices have really gone high in the country because of that. This should ease out in the coming 2 months to 3 months.”
In short
- 01H1 FY27 EBITDA was Rs 1,326 crore and PAT Rs 799 crore, the highest half-year EBITDA.
- 02The 600 MW thermal plant is expected to cross 420 crore units in FY27, after 202 crore units in H1.
- 03Management expects H2 thermal profitability substantially higher and hydro profitability lower due to season.
- 04Shutdown of one 300 MW unit cost about Rs 130-140 crore of revenue in Q2; no shutdown expected in H2.
- 05Environmental clearance to expand the thermal plant from 600 MW to 1,200 MW is expected this financial year.
- 06Company won the Avagudem manganese block; operations expected in about 12 to 14 months.
- 07Company is net debt-free with liquidity over Rs 2,600 crore; projects funded through internal accruals.
- 08Management does not give forward guidance on revenue or EBITDA.
Capex
Thermal power: Thermal brownfield expansion uses existing land, water and evacuation infrastructure
Pankaj Sarda · Managing Director · p. 5
Thermal power: Thermal brownfield expansion uses existing land, water and evacuation infrastructure
“This brownfield expansion remains one of our most capital-efficient growth opportunities, supported by existing land, water availability, material handling systems, and power evacuation infrastructure.”
Mining: Shahpur West coal mine commissioning targeted before end of this financial year
Pankaj Sarda · Managing Director · p. 5
Mining: Shahpur West coal mine commissioning targeted before end of this financial year
“On mining, development of the Shahpur West high-grade coal mine remains on schedule with commissioning targeted before the end of the current financial year.”
Mining: Bartunga Hill coal mine expected to open by end of next financial year
Pankaj Sarda · Managing Director · p. 5
Mining: Bartunga Hill coal mine expected to open by end of next financial year
“The Bartunga Hill coal mine also remains on schedule and is expected to be opened by the end of the next financial year.”
Mining: Approvals for Gare Palma IV/5 and Senduri coal blocks progressing as planned
Pankaj Sarda · Managing Director · p. 5
Mining: Approvals for Gare Palma IV/5 and Senduri coal blocks progressing as planned
“Regulatory approvals for the Gare Palma IV/5 and Senduri coal blocks continue to progress as planned.”
Capacity
Steel: Replaced Raipur turbogenerator running at full capacity since August 2026
Pankaj Sarda · Managing Director · p. 4
Steel: Replaced Raipur turbogenerator running at full capacity since August 2026
“megawatt turbogenerator commenced operations in August 2026 and is operating smoothly at full capacity, supporting captive power generation and steel production.”
Plans to quadruple mining capacity and double energy generation capacity
Manish Sarda · Deputy Chairman · p. 7
Plans to quadruple mining capacity and double energy generation capacity
“Our plans to quadruple mining capacity and double energy generation capacity are aligned with these opportunities.”
Segments
Thermal power: Thermal plant expected to see cost savings and higher generation after maintenance
Pankaj Sarda · Managing Director · p. 4
Thermal power: Thermal plant expected to see cost savings and higher generation after maintenance
“With the maintenance cycles of the last 2 years, we are now confident about the efficient functioning of the plant and expect both cost savings in the operation and higher generation going forward.”
Energy: Energy contributed more than 75% of H1 EBITDA
Manish Sarda · Deputy Chairman · p. 6
Energy: Energy contributed more than 75% of H1 EBITDA
“Energy’s contribution of more than 75% of H1 EBITDA demonstrates its importance to our earnings profile.”
Energy: H2: hydro profitability lower due to season; thermal substantially higher
Padam Jain · Q&A · p. 9
Energy: H2: hydro profitability lower due to season; thermal substantially higher
“In case of hydro, definitely in H2 profitability will be on lower side because of the seasonal conditionalities. And in thermal, it will be substantially higher because of the improved market conditions as well as higher generation in the second half.”
Thermal utilisation to improve in H2; pellet and sponge iron output to stay similar
Padam Jain · Q&A · p. 10
Thermal utilisation to improve in H2; pellet and sponge iron output to stay similar
“IPP thermal power plant, it will improve in the second half, as already stated. Because in the first half, capacity utilization was on lower side. In rest of the other plants, it depends, in case of steel plants. Iron ore pellet, it will remain more or less in the same line. Sponge iron also, it should remain in the same line.”
Steel: Billet and wire output depends on power prices; less steel when power pays more
Padam Jain · Q&A · p. 10
Steel: Billet and wire output depends on power prices; less steel when power pays more
“If we are selling power at remunerative prices, there may be a lower production. If we are getting normal price of power realization, then we may have a higher production in the steel billet and wire.”
Demand
India power generation grew 11% in the quarter; peak demand up 18% to 270 GW
Manish Sarda · Deputy Chairman · p. 6
India power generation grew 11% in the quarter; peak demand up 18% to 270 GW
“During the quarter, the country’s power generation grew 11% year-on-year to around 536 billion units. Peak power demand increased 18% to 270 GW, a new high for the second quarter.”
Steel: Steel demand strong, but high logistics cost makes next quarter unpredictable
Manish Sarda · Deputy Chairman · Q&A · p. 10
Steel: Steel demand strong, but high logistics cost makes next quarter unpredictable
“But we are facing a severe issue in terms of the logistics cost, because of high crude prices. So, next quarter is a little unpredictable, but the demand remains strong.”
Steel: Flat steel prices near Rs 75,000-77,000; long products near Rs 54,000 in places
Manish Sarda · Deputy Chairman · Q&A · p. 11
Steel: Flat steel prices near Rs 75,000-77,000; long products near Rs 54,000 in places
“If you looked at the prices of flat steel, they are close to INR75,000, INR77,000. And if you look at the long product pricing in Mumbai, in some places, they are even close to INR54,000.”
Energy: Current power market conditions better than in July and August
Padam Jain · Q&A · p. 13
Energy: Current power market conditions better than in July and August
“Furthermore, current market conditions are better than what we were seeing in the months of July and August.”
India solar generation up 39% year-on-year in the quarter
Manish Sarda · Deputy Chairman · p. 6
India solar generation up 39% year-on-year in the quarter
“Solar generation increased 39% year-on-year during the quarter, reflecting the pace of renewable energy development.”
Margins and costs
Captive power operations recalibrated in Q2 in line with market conditions
Pankaj Sarda · Managing Director · p. 3
Captive power operations recalibrated in Q2 in line with market conditions
“During Q2 FY27, we recalibrated captive power operations in line with market conditions, enabling us to optimize our portfolio mix.”
Ferro alloys: Manganese mine expected to save about Rs 200 to Rs 400 per ton
Speaker not named in the transcript · Q&A · p. 7
Ferro alloys: Manganese mine expected to save about Rs 200 to Rs 400 per ton
“So, we expect that in the next few months, we'll be having a clearer idea as to when we can start, with the paperwork being filed and everything done and it will roughly save around INR200 to INR400 per ton.”
Steel: South Africa coal freight about USD 36-38, up from usual USD 18-22
Manish Sarda · Deputy Chairman · Q&A · p. 10
Steel: South Africa coal freight about USD 36-38, up from usual USD 18-22
“Because different, like, all the imported coal that is coming from South Africa, the usual freights are normally around USD18 to USD22, for a 50,000 ton vessel. And currently, the freights are close to USD36, USD38 in terms of bulk freight.”
Captive coal mines partly insulate the company from coal costs
Manish Sarda · Deputy Chairman · Q&A · p. 11
Captive coal mines partly insulate the company from coal costs
“Yes, we do. We do have our own coal mines and we do meet our own requirements, so we are somewhat insulated.”
Thermal power: Q2 thermal power realisation about Rs 5.30 per unit
Padam Jain · Q&A · p. 12
Thermal power: Q2 thermal power realisation about Rs 5.30 per unit
“The thermal power realization was about INR5.30 in this quarter.”
Debt and working capital
Net debt-free; liquidity over Rs 2,600 crore; projects funded by internal accruals
Pankaj Sarda · Managing Director · p. 5
Net debt-free; liquidity over Rs 2,600 crore; projects funded by internal accruals
“We remain prudent in managing our balance sheet with all ongoing expansion projects funded through internal accruals. We remain net debt-free on both a standalone and a consolidated basis with liquidity exceeding INR2,600 crores as of 30th September 2026.”
CRISIL upgraded SEML to AA and Sarda Metals & Alloys to AA-
Pankaj Sarda · Managing Director · p. 5
CRISIL upgraded SEML to AA and Sarda Metals & Alloys to AA-
“Our financial strength was further reflected in an upgrade of SEML's credit rating by one notch, from AA- to AA and a two notch upgrade in Sarda Metals & Alloys Limited rating, from A to AA- by CRISIL.”
Acquisitions and new business
Ferro alloys: Preferred bidder for Avagudem manganese block in Andhra Pradesh
Pankaj Sarda · Managing Director · p. 3
Ferro alloys: Preferred bidder for Avagudem manganese block in Andhra Pradesh
“A key operational highlight this quarter was our entry into manganese ore mining, securing preferred bidder status for the Avagudem manganese block in Andhra Pradesh.”
Ferro alloys: Manganese mine has 4,50,000 tons of extractable reserves
Speaker not named in the transcript · Q&A · p. 7
Ferro alloys: Manganese mine has 4,50,000 tons of extractable reserves
“The total mine is 4,50,000 tons extractable reserves.”
Ferro alloys: Manganese mine gives low-grade ore security for four to five years
4–5yearsSpeaker not named in the transcript · Q&A · p. 7
Ferro alloys: Manganese mine gives low-grade ore security for four to five years
4–5years“The exact numbers will come out when we actually start mining. But it gives us the raw material security for our low-grade ores for the next four to five years.”
Ferro alloys: Company looking for more manganese mines in India and abroad
Manish Sarda · Deputy Chairman · Q&A · p. 8
Ferro alloys: Company looking for more manganese mines in India and abroad
“So, we are continuously on the lookout. And if there is an international opportunity for manganese as well, we are looking out for that.”
Ferro alloys: Avagudem was an operating mine; lease expired and it was won at auction
Manish Sarda · Deputy Chairman · Q&A · p. 8
Ferro alloys: Avagudem was an operating mine; lease expired and it was won at auction
“So, it was already operating mine. Somebody was already operating it. The lease has expired, and we have acquired it through the auction route.”
One-offs
Thermal power: About Rs 130-140 crore revenue lost in Q2 from shutdown of one thermal unit
Padam Jain · Q&A · p. 14
Thermal power: About Rs 130-140 crore revenue lost in Q2 from shutdown of one thermal unit
“200 crores from one unit, one quarter, so 25 crores unit, maybe about INR130 crores, INR140 crores of the revenue we have lost because of shutdown of the unit.”
Steel: Billet and wire rod plants not run in Q2 as power was sold in the market
Padam Jain · Q&A · p. 14
Steel: Billet and wire rod plants not run in Q2 as power was sold in the market
“Steel segment, we have not operated billet plant and wire rod plant because we were selling power in the market. That was the reason for shortfall in the revenue.”
Risks
Hydropower: Sikkim 113 MW hydro plant shut 18 June to 5 July after transmission tower collapse
Pankaj Sarda · Managing Director · p. 4
Hydropower: Sikkim 113 MW hydro plant shut 18 June to 5 July after transmission tower collapse
“day shutdown of the 113-megawatt Sikkim plant from 18th June to 5th July following a transmission tower collapse.”
Steel: Raw material squeeze expected from high coking coal prices and logistics
Manish Sarda · Deputy Chairman · Q&A · p. 11
Steel: Raw material squeeze expected from high coking coal prices and logistics
“So, there will be a little bit of a squeeze on the raw material side because of the logistics issues. But otherwise, I think the steel cycle looks to be good.”
Steel: Raw material squeeze depends on whether West Asia tensions ease logistics pressure
Manish Sarda · Deputy Chairman · Q&A · p. 11
Steel: Raw material squeeze depends on whether West Asia tensions ease logistics pressure
“So, we have seen a significant increase in terms of pricing, but we all have to assess in the next quarters how much the squeeze will be, whether the West Asia tensions would ease, because that will ease a lot of pressure in terms of logistics.”
Other
H1 FY27 EBITDA Rs 1,326 crore, up about 4%; PAT Rs 799 crore, up about 5%
Pankaj Sarda · Managing Director · p. 3
H1 FY27 EBITDA Rs 1,326 crore, up about 4%; PAT Rs 799 crore, up about 5%
“H1 FY27 marked the milestone for SEML, with the highest ever half yearly EBITDA of INR1,326 crores, up approximately 4% year-on-year and PAT of INR799 crores, up approximately 5%.”
H1 FY27 total income Rs 3,221 crore; cash profit Rs 1,225 crore
Pankaj Sarda · Managing Director · p. 3
H1 FY27 total income Rs 3,221 crore; cash profit Rs 1,225 crore
“Total income stood at INR3,221 crores, while cash profit increased to INR1,225 crores.”
Q2 FY27 EBITDA Rs 564 crore, PAT Rs 320 crore, total income Rs 1,505 crore
Pankaj Sarda · Managing Director · p. 3
Q2 FY27 EBITDA Rs 564 crore, PAT Rs 320 crore, total income Rs 1,505 crore
“The flexibility supported EBITDA of INR564 crores and PAT of INR320 crores, on total income of INR1,505 crores.”
Thermal power: One thermal unit is shut each year for about 30 to 40 days
Padam Jain · Q&A · p. 9
Thermal power: One thermal unit is shut each year for about 30 to 40 days
“As I told, every year we have to take shutdown of 1 unit for 30 days to 40 days, depending upon the condition of the unit.”
Thermal power: Thermal plant has two 300 MW units; each is shut in alternate years
Padam Jain · Q&A · p. 8
Thermal power: Thermal plant has two 300 MW units; each is shut in alternate years
“So, we have two power generating units of 300 megawatts each. And in alternate years, generally shutdown has to be taken for every unit.”
Sources
- Earnings call transcript, Q2 FY27 Filed 7 Nov 2026 · 16 pages
Management's own statements, quoted from its NSE filings. This page was read by AI and can contain mistakes: check the source pages before relying on any figure. No forecast or opinion of ours. Not investment advice.

