Results Q2 FY27, as filed · consolidated · ₹ Cr
| Q2 FY27 | Q2 FY26 | YoY | Q1 FY27 | QoQ | |
|---|---|---|---|---|---|
| Revenue | 1,609 | 1,238 | +30.0% | 1,624 | -0.9% |
| EBITDA | 179 | 147 | +21.6% | 167 | +6.9% |
| EBITDA margin | 11.1% | 11.9% | -77 bps | 10.3% | +81 bps |
| PBTProfit before tax | 128 | 112 | +14.5% | 126 | +1.6% |
| Net profit | 84 | 75 | +11.9% | 80 | +5.1% |
| EPS (₹) | 26.52 | 23.70 | +11.9% | 25.23 | +5.1% |
From the company's own results filing on NSE. Net profit is the owners' share. Growth and the dotted lines are worked out from the filed figures.
Guidance
No change to guidance; same EBITDA margin guidance for 2027 and 2028
N. Nani Aravind · Group Chief Financial Officer · Q&A · p. 11
No change to guidance; same EBITDA margin guidance for 2027 and 2028
“Right now, we are not proposing any changes in the guidance, sir. The guidance will remain same as what we projected earlier. In terms of the EBITDA margin also, the same guidance we are projecting for both 2027 and 2028.”
More figures from the call
“The KBP mine, we are targeting production around 3 million tons for the current financial year. Even though for our revenue guidance projection, we projected only 2.5 million tons.”
“We are short by only 2%-3% of the growth we have planned for the first half of the year, e. But we are confident of achieving the projected numbers.”
In short
- 01Q2 FY27 revenue was Rs 1,609 crore, up 30% year on year; EBITDA margin was 11.55% against 12.65%.
- 02FY27 order inflow target of Rs 12,000 crore; Rs 4,801 crore (about 40%) secured so far.
- 03Consolidated order backlog of Rs 56,729 crore, of which Rs 17,486 crore excluding MDO.
- 04FY27 guidance kept: at least 11.6% operating margin excluding other income; 12.25%-12.5% including other income.
- 05FY28 revenue growth expected at 25% to 30%, with mining ramp-up and Tasra production from March.
- 06MDO revenue expected above Rs 500 crore in FY27 (KBP Rs 350 crore, Tasra Rs 150 crore).
- 07Washery 85% built, construction to finish by end of January 2027, trial runs in February.
- 08Bid pipeline of about Rs 18,000 crore of high-probability cases plus about Rs 5,000 crore in steel.
Capex
MDO: Washery 85% built; construction to finish by end of January 2027, trials in February
N. Nani Aravind · Group Chief Financial Officer · p. 8
MDO: Washery 85% built; construction to finish by end of January 2027, trials in February
“Regarding the washery is concerned, we have completed 85% of the washery construction, and we are targeting to complete the construction of washery by end of January 2027. We are planning to start the trial runs in February.”
KBP mine: Little capex needed at KBP in next two years
N. Nani Aravind · Group Chief Financial Officer · Q&A · p. 10
KBP mine: Little capex needed at KBP in next two years
“In KBP, there is no requirement of much capex in next two years.”
MDO: Washery hoped to run by March, giving one month of washed coal revenue in FY27
N. Nani Aravind · Group Chief Financial Officer · Q&A · p. 8
MDO: Washery hoped to run by March, giving one month of washed coal revenue in FY27
“Hopefully, we will do the washery by March, and we will generate one month's revenue with washed coal during the current financial year.”
Order book
FY27 order inflow Rs 4,801 crore so far, about 40% of Rs 12,000 crore target
N. Nani Aravind · Group Chief Financial Officer · p. 4
FY27 order inflow Rs 4,801 crore so far, about 40% of Rs 12,000 crore target
“With this, the cumulative order inflow for FY27 up to the reporting period stood at INR4,801 crores, representing approximately 40% of our annual order inflow target of INR12,000 crores.”
Consolidated order backlog including MDO Rs 56,729 crore, up about 3%
N. Nani Aravind · Group Chief Financial Officer · p. 4
Consolidated order backlog including MDO Rs 56,729 crore, up about 3%
“As of today, our consolidated order backlog, including MDO projects, stood at INR56,729 crores, reflecting approximately 3% growth year-on-year.”
Order book excluding MDO about Rs 17,486 crore, over two years of revenue visibility
N. Nani Aravind · Group Chief Financial Officer · p. 4
Order book excluding MDO about Rs 17,486 crore, over two years of revenue visibility
“Of this, the executable order book, excluding MDO, stood at approximately INR17,486 crores, providing more than two years of revenue visibility across the core business.”
MDO: MDO order book about Rs 39,243 crore
N. Nani Aravind · Group Chief Financial Officer · p. 4
MDO: MDO order book about Rs 39,243 crore
“The MDO order book stood at approximately INR39,243 crores, representing a significant portion of our overall order backlog.”
Q2 FY27 fresh orders about Rs 1,890 crore
N. Nani Aravind · Group Chief Financial Officer · p. 4
Q2 FY27 fresh orders about Rs 1,890 crore
“the company secured fresh orders worth approximately INR1,890 crores during quarter two FY27.”
Segments
Industrial construction: Industrial construction revenue fell about 14% to Rs 372 crore on project completion, slow FGD
N. Nani Aravind · Group Chief Financial Officer · p. 3
Industrial construction: Industrial construction revenue fell about 14% to Rs 372 crore on project completion, slow FGD
“industrial construction recorded a revenue of INR372 crores during quarter two FY27 compared to INR435 crores in quarter two FY26, representing a decline of approximately 14% year-on-year. This was primarily due to completion of certain earlier projects and the slower progress in FGD projects.”
Industrial services: Industrial services revenue Rs 570 crore against Rs 440 crore
N. Nani Aravind · Group Chief Financial Officer · p. 3
Industrial services: Industrial services revenue Rs 570 crore against Rs 440 crore
“Industrial services recorded a revenue of INR570 crores compared to INR440 crores in the corresponding quarter of the previous year, registering a strong growth approximately 30%.”
Infrastructure construction: Infrastructure construction revenue Rs 582 crore against Rs 322 crore, up about 75%
N. Nani Aravind · Group Chief Financial Officer · p. 3
Infrastructure construction: Infrastructure construction revenue Rs 582 crore against Rs 322 crore, up about 75%
“Infrastructure construction contributed INR582 crores during the quarter compared to INR322 crores in quarter two FY26, registering a growth approximately 75%”
MDO: MDO revenue Rs 85 crore against Rs 31 crore, up about 174% on KBP ramp-up
N. Nani Aravind · Group Chief Financial Officer · p. 4
MDO: MDO revenue Rs 85 crore against Rs 31 crore, up about 174% on KBP ramp-up
“Our MDO business recorded a revenue of INR85 crores compared to INR31 crores in quarter two FY26, representing a growth of approximately 174% year-on-year. The growth was primarily supported by the ramp-up in production at the KBP mine.”
Company prefers private sector work for shorter cycles and quicker revenue
S.K. Ramaiah · Director (Non · p. 5
Company prefers private sector work for shorter cycles and quicker revenue
“Our business profile fits into more into private sector because of the quickness and also the shorter cycle times and the quick turnaround of the revenue, and that will give a better outlook for our operations in terms top and bottom line.”
Demand
Better outlook for 2026-2027 than 2025-2026 as more opportunities come up
S.K. Ramaiah · Director (Non · p. 5
Better outlook for 2026-2027 than 2025-2026 as more opportunities come up
“one significant thing is that there is a better outlook in the year 2026-2027 compared to 2025-2026, from the fact is that more opportunities are coming up.”
Power: Adani plans 18,730 MW to 42,000 MW in five years; JSW 5,658 MW to 30,000 MW
S.K. Ramaiah · Director (Non · p. 5
Power: Adani plans 18,730 MW to 42,000 MW in five years; JSW 5,658 MW to 30,000 MW
“Adani is planning of the capacity enhancement ongoing projects from what is the installed capacity, 18,730 MW to 42,000 MW in the next five years. JSW is planning from 5,658 MW to 30,000 MW.”
Power: Ongoing power projects of 59,000-60,000 MW with Rs 3 lakh crore investment
S.K. Ramaiah · Director (Non · p. 7
Power: Ongoing power projects of 59,000-60,000 MW with Rs 3 lakh crore investment
“ongoing projects which are working in various projects about 59,000 MW- 60,000 MW with an investment of INR3 lakh crores.”
O&M: New power plants may add Rs 1,200-1,500 crore of O&M opportunity yearly
S.K. Ramaiah · Director (Non · p. 7
O&M: New power plants may add Rs 1,200-1,500 crore of O&M opportunity yearly
“That may add an opportunity in the O&M side, offering about INR1,200 crore-INR1,500 crores yearly apart from the renewals.”
Power: Private sector investment, led by Adani and JSW, named as main driver
S.K. Ramaiah · Director (Non · p. 5
Power: Private sector investment, led by Adani and JSW, named as main driver
“The main driver is the investments which are coming in a massive way by the private sector. Adani and then JSW, they are leading the pack, the whole aspect.”
Margins and costs
Q2 FY27 EBITDA margin 11.55% against 12.65% a year earlier
N. Nani Aravind · Group Chief Financial Officer · p. 4
Q2 FY27 EBITDA margin 11.55% against 12.65% a year earlier
“Coming to the margins and profitability, EBITDA margin quarter two FY27 stood at 11.55% compared to 12.65% in quarter two FY26.”
PAT about Rs 2 crore lower than Q1 due to higher finance cost and depreciation
N. Nani Aravind · Group Chief Financial Officer · p. 4
PAT about Rs 2 crore lower than Q1 due to higher finance cost and depreciation
“On a sequential basis, PAT was marginally lower by approximately INR2 crores, mainly due to higher finance cost and depreciation during the quarter.”
Margins expected to improve in coming quarters as MDO share grows
N. Nani Aravind · Group Chief Financial Officer · p. 4
Margins expected to improve in coming quarters as MDO share grows
“Looking ahead, we expect the margin trajectory to improve in the coming quarters as the contribution from relatively higher-margin business, particularly MDO, increases with the scaling up of operations.”
MDO: Rainy season cut mining output; margins expected to recover as volume rises
N. Nani Aravind · Group Chief Financial Officer · Q&A · p. 10
MDO: Rainy season cut mining output; margins expected to recover as volume rises
“Maybe because of the rainy season in the mining side, there is a low production, and once the volume increases, the margins will be recovered in the minimum of that.”
Contract execution costs rose with 30% revenue growth and new EPC and HAM work
N. Nani Aravind · Group Chief Financial Officer · Q&A · p. 13
Contract execution costs rose with 30% revenue growth and new EPC and HAM work
“The one is the revenue has increased almost 30% compared to the previous year. Plus, we have started doing this EPC construction and HAM project or EPC construction and all, so the contract execution expenses have increased.”
Debt and working capital
About Rs 400 crore invested in washery and new assets, funded by equipment loans
N. Nani Aravind · Group Chief Financial Officer · Q&A · p. 13
About Rs 400 crore invested in washery and new assets, funded by equipment loans
“Subsequently, in months we have put on the money, and we have almost invested around INR400 crores on the new assets, the washery and the new capex requirements. For that, we raised equipment loans, and the working capital utilization has increased.”
Net current assets kept at about 120 days
N. Nani Aravind · Group Chief Financial Officer · Q&A · p. 13
Net current assets kept at about 120 days
“Overall average net current assets, we are maintaining at 120 days level.”
Finance cost rose on capex equipment loans; expected to come down
N. Nani Aravind · Group Chief Financial Officer · Q&A · p. 16
Finance cost rose on capex equipment loans; expected to come down
“The majorly capex and the new equipment loans we have taken during the quarter for the new capex requirements, so that resulted in the higher finance cost. But going forward, this cost will come down.”
Use of borrowing limits fell in Q3 compared to September
N. Nani Aravind · Group Chief Financial Officer · p. 16
Use of borrowing limits fell in Q3 compared to September
“The utilization of limits has reduced during Q3 compared to September (Q2)”
Collections take 45-60 days depending on the division
N. Nani Aravind · Group Chief Financial Officer · Q&A · p. 13
Collections take 45-60 days depending on the division
“The collection is 45- 60 days it is taking, depends on the division.”
Acquisitions and new business
Steel: Bhilai steel raw material handling EPC package of Rs 4,000-4,500 crore; partner tie-up sought
S.K. Ramaiah · Director (Non · p. 7
Steel: Bhilai steel raw material handling EPC package of Rs 4,000-4,500 crore; partner tie-up sought
“Initial tenders are out in the case of Bhilai Steel Plant for the raw material handling package that will be around combined EPC package of INR4,000 crore-INR4,500 crores. We are trying to tie up with a technology partner on that.”
International: Rs 492 crore 2,000 MW gas combined cycle plant installation order won in Saudi Arabia
S.K. Ramaiah · Director (Non · p. 7
International: Rs 492 crore 2,000 MW gas combined cycle plant installation order won in Saudi Arabia
“Latest information is that we have taken a INR492crores combined cycle plant, 2,000 MW Gas fired combined Cycle power plant installation work in Saudi Arabia. Just now that order has been clinched.”
Steel: Steel tie-up talks with Thyssenkrupp; company portion about Rs 2,000 crore per package
S.K. Ramaiah · Director (Non · Q&A · p. 15
Steel: Steel tie-up talks with Thyssenkrupp; company portion about Rs 2,000 crore per package
“That we have to make some tie-ups with the technology players like Thyssenkrupp. We are discussing on that. That will definitely bring a substantial business because the package size around INR2,000 crores for our portion in each case.”
Data centres: Exploring data centres as diversification; talks with developers
S.K. Ramaiah · Director (Non · p. 18
Data centres: Exploring data centres as diversification; talks with developers
“Of course, lot of things have to be learned on that. The technology of it, the implementation of it, we are discussing with some developers on that also.”
One-offs
Last year's margin was higher due to exceptional Uttarakhand riverbed mineral revenue
N. Nani Aravind · Group Chief Financial Officer · p. 4
Last year's margin was higher due to exceptional Uttarakhand riverbed mineral revenue
“Higher margins during the previous year, due to exceptional additional revenues in Uttarakand Riverbed minerals the comparative number is higher compared to the present quarter.”
Risks
International: Middle East and West Africa opportunities depend on peace continuing
S.K. Ramaiah · Director (Non · p. 7
International: Middle East and West Africa opportunities depend on peace continuing
“Therefore, lot more opportunities to come into Middle East and also West Africa provided the present peace can continue.”
Material costs rose due to the war in West Asia
N. Nani Aravind · Group Chief Financial Officer · Q&A · p. 10
Material costs rose due to the war in West Asia
“There is a constraint in terms of increase of the material cost on account of the war in West Asia.”
Water: Jal Jeevan Mission bill certification delayed; about Rs 150 crore WIP pending
N. Nani Aravind · Group Chief Financial Officer · Q&A · p. 14
Water: Jal Jeevan Mission bill certification delayed; about Rs 150 crore WIP pending
“Right now, there are no issues of payment except that Jal Jeevan Mission water division, there is a delay in certification of the bills. All Receivables were realised, and approximately INR150 crores of Work in Progress are right now pending for certification.”
BHEL and L&T split packages; such projects likely to see more delay
S.K. Ramaiah · Director (Non · Q&A · p. 15
BHEL and L&T split packages; such projects likely to see more delay
“By splitting the packages from one or two packages, they are making to four, five, six like that. That will not exactly fit in. Those projects will definitely get more delayed.”
Other
Q2 FY27 revenue from operations Rs 1,609 crore, up 30% year on year
N. Nani Aravind · Group Chief Financial Officer · p. 3
Q2 FY27 revenue from operations Rs 1,609 crore, up 30% year on year
“recorded a revenue from operations of INR1,609 crores, registering a strong year-on-year growth of 30% compared to INR1,238 crores in quarter two of financial year 2026.”
H1 FY27 revenue from operations Rs 3,233 crore, up 28%
N. Nani Aravind · Group Chief Financial Officer · p. 3
H1 FY27 revenue from operations Rs 3,233 crore, up 28%
“For the first half of financial year 2027, revenue from operations stood at INR3,233 crores, registering a growth of 28% over INR2,531 crores in the corresponding period of the previous year.”
EBITDA rose from Rs 176 crore in Q1 to Rs 187 crore in Q2 FY27
N. Nani Aravind · Group Chief Financial Officer · p. 4
EBITDA rose from Rs 176 crore in Q1 to Rs 187 crore in Q2 FY27
“On sequential basis, EBITDA improved approximately INR11 crores. From INR176 crores in Q1 FY27 to INR187 crores in Q2 FY27.”
Q2 FY27 PAT Rs 88 crore against Rs 78 crore, up about 12%
N. Nani Aravind · Group Chief Financial Officer · p. 3
Q2 FY27 PAT Rs 88 crore against Rs 78 crore, up about 12%
“Profit after tax for quarter two FY27 stood at INR88 crores compared to INR78 crores in quarter two FY26, registering a growth approximately 12%.”
Priorities: faster execution, higher O&M and MDO share, better cash flows
N. Nani Aravind · Group Chief Financial Officer · p. 5
Priorities: faster execution, higher O&M and MDO share, better cash flows
“Our key priorities for the coming quarter will be to accelerate execution across all our existing order book and newly secured projects, improve our margin profile through a higher contribution from O&M and MDO business, strengthen cash flows through a timely project certification, collection, and efficient working capital management”
Sources
- Earnings call transcript, Q2 FY27 Filed 17 Nov 2026 · 19 pages
Management's own statements, quoted from its NSE filings. This page was read by AI and can contain mistakes: check the source pages before relying on any figure. No forecast or opinion of ours. Not investment advice.