Capital Goods · NSE: POWERINDIA

Hitachi Energy India

Price as of 12 Nov 2026
28,545.00−1.91%

Q1 FY27 earnings call · Guided by management

Call held 7 Aug 2026 · Read the filing on NSEFiling

6​GWClean electricity delivered by linksNuguri · p. 6
56​baysGIS bays orderedNuguri · p. 6
6​monthsExpected HVDC award timing · HVDCNuguri · Q&A · p. 13
15​GWData center capacity by 2030 · Data center · by 2030Nuguri · Q&A · p. 15
M.Cap
₹1,27,232Cr₹1.27L Cr
P/E
110.6×
1Y return
+29.64%
From 52W high
−26.4%

Highlights are read by AI from the company's filing and can contain mistakes. Check the source page linked to each line.

Share price

Results Q1 FY27, as filed · standalone · ₹ Cr

Q1 FY27Q1 FY26YoYQ4 FY26QoQ
Revenue2,4941,479+68.6%2,754-9.5%
EBITDA364155+134.7%416-12.7%
EBITDA margin14.6%10.5%+411 bps15.1%-54 bps
PBTProfit before tax390177+120.2%443-12.1%
Net profit294132+123.5%330-11.0%
EPS (₹)65.9929.53+123.5%74.14-11.0%

From the company's own results filing on NSE. Net profit is the owners' share. Growth and the dotted lines are worked out from the filed figures.

More figures from the call

Company · Other
3–4​percentage pointsGender diversity improvement · by 2030
“Gender diversity increased from 5.8% to over 10%, reinforcing our commitment to building a more inclusive workplace. We are targeting a further improvement of 3-4 percentage points by 2030.”
Venu Nugurip. 4
Company · Other
0.09​rateRecordable injury frequency rate target
“Through these efforts, we remain focused on achieving a recordable injury frequency rate of 0.09.”
Venu Nugurip. 4

In short

  1. 01Q1 FY27 orders were INR 5,096.5 crore; excluding HVDC, order intake rose 26.1% YoY.
  2. 02Order backlog stood at INR 32,222.1 crore at quarter end.
  3. 03Revenue rose 68.6% YoY to INR 2,493.7 crore; operational EBITDA rose 135.0% to INR 399.9 crore.
  4. 04EBITDA includes an unrealised foreign exchange loss of INR 36.37 crore.
  5. 05Construction of the 20th factory at Karjan, Vadodara began in June 2026, targeting commissioning in December 2028.
  6. 06First BESS order (165 MW / 330 MWh, Andhra Pradesh) won; margin profile not yet given.
  7. 07A greenfield HVDC project under bidding is expected to be awarded in 6 months.
  8. 08Gross margin contracted YoY due to product mix; HVDC revenue to pick up in second and third year.

Capex

Construction of 20th factory at Karjan, Vadodara began in June 2026

Venu Nuguri · p. 3
“As part of our commitment to strengthen execution capabilities and building a more resilient supply chain, we began construction of Hitachi Energy India's 20th manufacturing facility in Karjan, Vadodara in June 2026.”

Karjan factory targeted for commissioning in December 2028

Venu Nuguri · p. 8
“With a targeted commissioning date of December 2028, the facility will play a key role in expanding our manufacturing footprint, strengthening local capabilities, and supporting the growing demand for sustainable energy infrastructure in India and global markets.”

Capex aims to raise capacity and localise components

Venu Nuguri · Q&A · p. 12
“Our capex is to increase our capacity and of course, localizing some of those components. I do not see any issue in competing with any of those players.”

Capex aims at end-to-end manufacturing in India with more localized components

Venu Nuguri · Q&A · p. 13
“It is the volume and other things will give us leverage. the whole idea is to localize more components and to create an end-to-end manufacturing scenario over a period in India. That is our intention of doing this kind of capex.”

Order book

Orders of INR 5,096.5 crore secured in Q1 FY27

Venu Nuguri · p. 5
“Against this market backdrop, we secured orders worth INR 5,096.5 crs during Q1 FY27.”

Order intake excluding HVDC up 26.1% YoY and 39.7% QoQ

Venu Nuguri · p. 5
“Q1 FY26 included a large HVDC order, therefore, to provide a more meaningful comparison of our underlying performance, we have also presented order growth excluding HVDC for the current quarter. On a comparable basis, order intake in Q1 FY27 increased by 26.1% YoY and 39.7% QoQ”

Order backlog of INR 32,222.1 crore at end of Q1 FY27

Venu Nuguri · p. 5
“As a result, we closed the quarter with an order backlog of INR 32,222.1 crs, representing strong double-digit growth compared with Q1 FY26 and providing good revenue visibility for the coming quarters.”

Data center: Multiple data center orders from hyperscalers, incl. 40 × 2500 kVA in Hyderabad

Venu Nuguri · p. 5
“In addition, we secured multiple data center orders from hyperscalers during the quarter. A notable project among these is a 40 × 2500 kVA data center project in Hyderabad, awarded by a leading Indian multinational conglomerate.”

Most Q1 orders were base orders; no major large orders

Venu Nuguri · Q&A · p. 11
“Most of them are base orders. We do not have any major large orders this quarter. We have seen strong order from the data center this quarter.”

Segments

Battery Energy Storage System: BESS focus on domestic market for now; scale-up after technology validated

Venu Nuguri · Q&A · p. 10
“And right now, our focus is to supply for the domestic market. We have just started. We first need to validate the technology we have deployed and then we will scale it up slowly. However, order pipeline is quite robust.”

HVDC: HVDC revenue lower in first year, to pick up in second and third year

Ajay Singh · Chief Financial Officer · Q&A · p. 12
“If you have been following us, we have been telling that the first year, the revenue execution will be slightly on the lower side, and then it will pick up from the second and third year. That is what we have been telling. Hence, the full revenue contribution from the HVDC projects has not yet materialized.”

HVDC: Khavda HVDC project picking up; Bhadla project starting

Venu Nuguri · Q&A · p. 12
“The first project, Khavda project is picking up. Bhadla project is starting.”

Transmission; Railway and metro: Transmission dip temporary; railway orders expected to pick up in second half

Venu Nuguri · Q&A · p. 14
“It is a temporary thing in the transmission. I do not see that as any major issue. Railway projects are progressing slower than originally anticipated. Based on the discussion with the rail and metro authorities -- we expect it should pick from the second half of the year.”

Battery Energy Storage System: BESS PCS solutions not yet localised; end-to-end offering excludes batteries

Venu Nuguri · Q&A · p. 13
“In one approach, we also supply our PCS solutions, which we are not localized yet.”

Demand

Order pipeline cited across domestic and export; transmission, RE evacuation, data centers drove inflow

Venu Nuguri · p. 4
“We are particularly encouraged by the strength of the current order pipeline across both domestic and export markets. During the quarter, transmission projects, renewable energy evacuation initiatives, and the growing data center segment were key drivers for order inflow.”

India electricity demand expected to grow over the coming decade; AI workloads a new driver

Venu Nuguri · p. 5
“India's electricity demand is expected to grow strongly over the coming decade. In parallel, the power grid is becoming increasingly complex, with higher load densities, rising reliability requirements, and emerging demand drivers such as AI-enabled workloads.”

Market drivers named: renewables, transmission, industrial capex, data centers, EVs, DISCOMs

Venu Nuguri · p. 5
“Our addressable market continues to present significant opportunities, and we see strong momentum in renewable energy, substantial transmission investments to integrate non-fossil fuel capacity, a visible industrial capex cycle, increasing investments in data centers, and accelerating adoption of electric vehicles. In addition, improving DISCOM fundamentals are supporting higher investments in distribution infrastructure.”

Data center: Data center customers securing long-lead items; portfolio covers full grid integration

Venu Nuguri · Q&A · p. 14
“Most of the data center customers are securing the long lead items like dry transformer, the GIS, etcetera. Our portfolio will be the entire grid integration which includes GIS, the transformers, the dry transformer, the power transformers including the services.”

Battery Energy Storage System: Storage mandate for renewables driving domestic BESS opportunities

Venu Nuguri · Q&A · p. 10
“It has been mandated that every renewable energy needs to have energy storage. So, all those things are driving the huge amount of growth opportunities in domestic market.”

Margins and costs

PBT up 120.2% YoY; operational EBITDA up 135.0% to INR 399.9 crore

Ajay Singh · Chief Financial Officer · p. 8
“From a profitability perspective, disciplined execution and operating leverage resulted in a 120.2% YoY increase in Profit Before Tax (PBT), while operational EBITDA grew 135.0% YoY to INR 399.9 crs.”

Material costs as share of revenue kept within historical range

Ajay Singh · Chief Financial Officer · p. 8
“Despite the evolving geopolitical environment, we have been able to maintain material costs as a percentage of revenue within the historical range during Q1 FY27.”

Depreciation rose QoQ due to capacity expansion capex; finance cost stable

Ajay Singh · Chief Financial Officer · p. 8
“Depreciation has increased compared to the previous quarter reflecting ongoing capital expenditure towards capacity expansion. Finance cost remained broadly stable.”

PBT margin 15.6% and PAT margin 11.8% in Q1 FY27

Ajay Singh · Chief Financial Officer · p. 8
“As a result, our profit before tax margin stood at 15.6%, while profit after tax margin was 11.8%.”

Battery Energy Storage System: BESS margin profile not stated; margins to reach desired levels over time

Venu Nuguri · Q&A · p. 10
“The margin profile is difficult to mention at this stage as this technology needs to mature. We need to do a lot of localization in this segment. Over time, these margins will gradually reach the desired levels.”

Acquisitions and new business

Battery Energy Storage System: First BESS order: 165 MW / 330 MWh project in Andhra Pradesh

Venu Nuguri · p. 6
“The second project marks a major milestone for Hitachi Energy India. It is a 165 MW / 330 MWh Battery Energy Storage System (BESS) project in Andhra Pradesh, reflecting strong validation of our capabilities in grid integration, power quality, and advanced energy solutions.”

Data center: Launched "Grid to rack solution for data centres"

Venu Nuguri · Q&A · p. 14
“In our portfolio, we have just launched “Grid to rack solution for data centres.” We have shown the same in our investors meet in Mumbai.”

One-offs

EBITDA includes unrealised foreign exchange loss of INR 36.37 crore

Ajay Singh · Chief Financial Officer · p. 8
“It is important to note that this EBITDA performance includes an unrealized foreign exchange loss of INR 36.37 crs recorded during the quarter.”

Risks

No material impact seen from entry of Chinese players in transformers and GIS

Venu Nuguri · Q&A · p. 13
“Coming back to the specific question i.e., transformer and GIS. They were already competing in some form or other form, may not be in same segment, hence, I do not see any material impact for us.”

More competition welcome; expects to meet margin ambition with level playing field

Venu Nuguri · Q&A · p. 13
“More competition is welcome to meet the demand and supply challenges or perceived demand and supply challenges, if any. As long as there is a level playing field, we do not see any issue in competing and ensuring that our margin ambition is met in that.”

Closing remarks: demand robust, pipeline larger; macro and execution risks noted

Venu Nuguri · p. 15
“The business is executing well, market demand remains robust, and our pipeline is stronger than ever. While we remain mindful of macroeconomic uncertainties and project execution challenges that can arise in a dynamic environment, we are confident in our ability to capitalize on the opportunities ahead and continue creating long-term value for our shareholders.”

Other

Revenue grew 68.6% YoY in Q1 FY27

Ajay Singh · Chief Financial Officer · p. 8
“We delivered strong revenue growth of 68.6% YoY, driven by robust execution of our order backlog.”

Revenue from operations INR 2,493.7 crore; other income about INR 57 crore

Ajay Singh · Chief Financial Officer · p. 8
“This slide highlights that revenue from operations was INR 2,493.7 crs, while other income was approximately INR 57 crs, primarily comprising interest income on deposits.”

Exports: Exports are around 25% of revenue

Ajay Singh · Chief Financial Officer · Q&A · p. 10
“Export contribution on the revenues is around 25%. So that is the run rate we are seeing now.”

Exports: Exports trending at 25% - 26%

Venu Nuguri · Q&A · p. 12
“On the exports we are trending 25% - 26%.”

Freshwater usage cut 16% versus 2019 baseline

Venu Nuguri · p. 4
“During the year, we achieved a 16% reduction in freshwater usage compared with the 2019 baseline through recycling initiatives and the deployment of water-efficient fixtures.”