Q2 FY27 earnings and concall highlights
Q2 FY27 earnings call · Guided by management
Call held 29 Oct 2026 · Read the filing on NSEFiling
- M.Cap
- ₹3,277Cr
- P/E
- 5.2×
- 1Y return
- −53.39%
- From 52W high
- −53.4%
Highlights are read by AI from the company's filing and can contain mistakes. Check the source page linked to each line.
Share price
Results Q2 FY27, as filed · consolidated · ₹ Cr
| Q2 FY27 | Q2 FY26 | YoY | Q1 FY27 | QoQ | |
|---|---|---|---|---|---|
| Revenue | 1,322 | 1,128 | +17.3% | 1,688 | -21.7% |
| EBITDA | 279 | 253 | +10.2% | 524 | -46.7% |
| EBITDA margin | 21.1% | 22.4% | -136 bps | 31.0% | -993 bps |
| One-off items | — | 163 | — | — | — |
| PBTProfit before tax | 158 | 292 | -46.1% | 432 | -63.5% |
| Net profit | 115 | 216 | -46.9% | 332 | -65.5% |
| EPS (₹) | 4.47 | 8.41 | -46.8% | 12.94 | -65.5% |
From the company's own results filing on NSE. Net profit is the owners' share. Growth and the dotted lines are worked out from the filed figures.
Guidance
HAM: New NHAI HAMs: 35-40% progress expected in FY28 and 60% in FY29
T. R. Rao · Q&A · p. 15
HAM: New NHAI HAMs: 35-40% progress expected in FY28 and 60% in FY29
“So FY28, we expect 35% to 40% progress and the 60% progress in FY29.”
Management says there is no change in revenue and margin guidance
T. R. Rao · Q&A · p. 7
Management says there is no change in revenue and margin guidance
“No, as of now, there is no change. We will maintain the same guidance.”
International: No international orders assumed in the current financial year
T. R. Rao · Q&A · p. 15
International: No international orders assumed in the current financial year
“As of now, we are not considering any order from the international market in the current financial year.”
Order inflow guidance for the year to remain the same
T. R. Rao · Q&A · p. 7
Order inflow guidance for the year to remain the same
“Yeah, will remain same.”
In short
- 01FY27 revenue guidance of about Rs 6,000 crore kept, including the arbitration award.
- 0212% EBITDA margin guided on Rs 5,800 crore revenue, excluding the arbitration claim.
- 03FY28 revenue guided at Rs 7,500 crore, about 25% over FY27.
- 04FY27 order inflow guidance of Rs 12,000-15,000 crore kept; Rs 4,260 crore won so far.
- 05Unexecuted order book over Rs 18,000 crore; 63% highways.
- 06NHPC battery storage (BESS) award cancelled as agreements were not signed; bid security refunded.
- 07Delhi High Court stayed NHAI debarment orders; next hearing on 26th November.
- 08Coal mining and water revenue for FY27 lowered; management is considering a buyback.
Capex
Capex of Rs 155 crore made so far; total FY27 capex Rs 200 crore
Pankaj Agarwal · Vice President · Q&A · p. 20
Capex of Rs 155 crore made so far; total FY27 capex Rs 200 crore
“We have made the capex of INR155 crores, and for balance period, we are going to total amount is INR200 crores.”
Order book
50-60% of expected new orders from NHAI, MoRTH, NHIDCL; 30-40% from others
T. R. Rao · Q&A · p. 20
50-60% of expected new orders from NHAI, MoRTH, NHIDCL; 30-40% from others
“More than 50% to 60% from the NHAI and MoRTH and, I think, NHIDCL, and 30% to 40% would be from the non-NHAI.”
Unexecuted order book stands at over Rs 18,000 crore
Yogesh Jain · Managing Director · p. 5
Unexecuted order book stands at over Rs 18,000 crore
“Company’s unexecuted order book, including newly secured two NHAI HAM projects, stands at over INR 18,000 crores.”
Order book mix: highways 63%, water/canal/railway/airport 21%, coal mining 16%
Yogesh Jain · Managing Director · p. 5
Order book mix: highways 63%, water/canal/railway/airport 21%, coal mining 16%
“Highway contracts contribute 63% of total unexecuted order book, while water, canal, railway and airport contracts contribute around 21%, and coal mining contract contributes 16%.”
Order book of Rs 15,000 crore expected at year end even without new orders
T. R. Rao · p. 11
Order book of Rs 15,000 crore expected at year end even without new orders
“And going forward also, even at the end of the current financial year, still we'll having an opening balance of INR15,000 crores of unexecuted order book, even if you don't consider any new orders.”
17 bids worth Rs 16,600 crore submitted; price bids yet to be opened
Yogesh Jain · Managing Director · p. 5
17 bids worth Rs 16,600 crore submitted; price bids yet to be opened
“On bidding front, we have submitted 17 bids to different authorities for a total estimated cost of Rs. 16,600 crore, price bids of which are yet to be opened.”
Segments
International: International: targeting 12-12.5% EBITDA, similar to domestic
T. R. Rao · p. 19
International: International: targeting 12-12.5% EBITDA, similar to domestic
“we are targeting the similar kind of return, what we are making at 12% to 12.5% EBITDA in the domestic.”
International: Bid submitted for a road project in Georgia in September 2026
Yogesh Jain · Managing Director · p. 5
International: Bid submitted for a road project in Georgia in September 2026
“As part of the Company’s endeavor to expand into international markets, the Company submitted a bid for a road project in Georgia to the Roads Department under the Ministry of Infrastructure of Georgia in September 2026.”
International: Also pursuing opportunities in Uzbekistan and the UAE
T. R. Rao · p. 10
International: Also pursuing opportunities in Uzbekistan and the UAE
“And apart from Kazakhstan, we also pursuing opportunities in Uzbekistan as well as the United Arab Emirates.”
International: International projects need no significant capital except working capital
T. R. Rao · p. 13
International: International projects need no significant capital except working capital
“So, even if the international project also, there won't be any significant capital requirement except working capital needs.”
Highways remain core focus while expanding into other core sectors
Yogesh Jain · Managing Director · p. 4
Highways remain core focus while expanding into other core sectors
“While highways will continue to remain our core focus sector, we are actively expanding into other core sectors to build a broader, more resilient order book that supports long-term sustainable growth.”
Demand
Less competition expected in large projects and fund-based projects like HAM
T. R. Rao · p. 11
Less competition expected in large projects and fund-based projects like HAM
“We see that the competition will be lesser in the large-scale, large-size projects and where there's a fund-based projects like HAM and other kind of a thing where the investment needs to be made.”
Highways: NHAI awarded about 230 route km in Q2 FY27 vs 107 km in Q1
Yogesh Jain · Managing Director · p. 3
Highways: NHAI awarded about 230 route km in Q2 FY27 vs 107 km in Q1
“During Q2 of FY27, NHAI awarded highway projects of approximately 230 route kilometers, compared to 107 route kilometers awarded in Q1 of FY27.”
Highways: Of 54 NHAI projects for award in FY27, 19 approved and 17 appraised
Yogesh Jain · Managing Director · p. 3
Highways: Of 54 NHAI projects for award in FY27, 19 approved and 17 appraised
“Out of the 54 projects identified by NHAI for awarding during the remaining period of FY27, 19 projects have received approval, while another 17 have been appraised and balance projects are expected to receive approvals shortly.”
Highways: Highways sector showed signs of recovery in Q2 FY27 after two slow years
Yogesh Jain · Managing Director · p. 3
Highways: Highways sector showed signs of recovery in Q2 FY27 after two slow years
“The highways sector started showing signs of recovery in Q2 of FY27 after significant slowing down in project awarding activity persisted over the past two years.”
Highways: Government considering about 51,000 km of high-speed corridors over the next decade
Yogesh Jain · Managing Director · p. 3
Highways: Government considering about 51,000 km of high-speed corridors over the next decade
“As the government is considering development of approximately 51,000 kilometers of high-speed corridors across the country over the next decade, a large number of new business opportunities are expected to emerge for highway developers.”
Margins and costs
Higher crude prices from West Asia conflict raised diesel and bitumen costs
Yogesh Jain · Managing Director · p. 4
Higher crude prices from West Asia conflict raised diesel and bitumen costs
“Rising crude oil prices on account of the West Asia conflict have increased costs for key inputs including diesel and bitumen, straining procurement, transport, construction, and equipment operations severely.”
Price escalation mechanism extended to December 31, 2026, but mitigates only partly
Yogesh Jain · Managing Director · p. 4
Price escalation mechanism extended to December 31, 2026, but mitigates only partly
“Though MoRTH, NHAI and AAI have extended the monthly price-adjustment escalation mechanism for eligible EPC and HAM projects through December 31, 2026, the actual impact of financial mitigation is effective only to a limited extent.”
Margin guidance already takes bitumen cost impact into account
Yogesh Jain · Managing Director · Q&A · p. 12
Margin guidance already takes bitumen cost impact into account
“Yeah. It is already taken.”
Input cost inflation and partial escalation cover pressure infra players' margins
Yogesh Jain · Managing Director · p. 4
Input cost inflation and partial escalation cover pressure infra players' margins
“Consequently, persistent input cost inflation and partial escalation coverage continue to exert pressure on the operating margins of infrastructure players.”
Debt and working capital
HAM: Internal accruals expected to cover balance HAM equity
Yogesh Jain · Managing Director · p. 5
HAM: Internal accruals expected to cover balance HAM equity
“Internal accruals that would be generated over the next two to three years should be adequate to meet the balance equity investment requirement.”
Cash in PNC Infra Holdings is Rs 1,115 crore
Pankaj Agarwal · Vice President · Q&A · p. 14
Cash in PNC Infra Holdings is Rs 1,115 crore
“Total cash in PNC Infra Holdings is INR1,115 crores.”
Standalone net worth Rs 6,143 crore; standalone debt Rs 1,312 crore
Yogesh Jain · Managing Director · p. 6
Standalone net worth Rs 6,143 crore; standalone debt Rs 1,312 crore
“On Standalone basis, our net worth as on 30th September 2026 is Rs. 6,143 crores, whereas standalone debt from Banks/ Financial Intuitions and Intra Corporate Deposits is Rs. 1,312 crores.”
Standalone net debt to equity is 0.10 after cash and investments
Yogesh Jain · Managing Director · p. 7
Standalone net debt to equity is 0.10 after cash and investments
“Considering the total cash & bank balance including current investments, the net debt-equity ratio on standalone basis comes to 0.10.”
Consolidated net worth Rs 7,248 crore; total debt Rs 5,912 crore
Yogesh Jain · Managing Director · p. 7
Consolidated net worth Rs 7,248 crore; total debt Rs 5,912 crore
“On Console basis, our net worth as on 30th September 2026 is Rs. 7,248 crores whereas total debt is Rs. 5,912 crores.”
Acquisitions and new business
International: Subsidiary incorporated in Kazakhstan to explore international growth
Yogesh Jain · Managing Director · p. 5
International: Subsidiary incorporated in Kazakhstan to explore international growth
“To explore international growth beyond the domestic market, the Company has incorporated a subsidiary, PNC Infratech (Kazakhstan) LLP, in Republic of Kazakhstan.”
12 assets monetised for Rs 2,517 crore; Rs 158 crore still to be received
Pankaj Agarwal · Vice President · Q&A · p. 15
12 assets monetised for Rs 2,517 crore; Rs 158 crore still to be received
“The total consideration we received from the monetization of 12 asset is INR2,517 crores. Out of that, INR158 crores is yet to be received from the seller (to be read as buyer).”
Dividends and buybacks
Management says it is thinking about a buyback
Yogesh Jain · Managing Director · Q&A · p. 12
Management says it is thinking about a buyback
“Yeah. We are thinking in the same line to buy back.”
One-offs
Rs 244 crore arbitration award in company's favour for Sonauli-Gorakhpur project
Yogesh Jain · Managing Director · p. 5
Rs 244 crore arbitration award in company's favour for Sonauli-Gorakhpur project
“On 31st July 2026, an arbitration award was published in favour of the Company for Rs. 244 crores in connection with an EPC project of Sonauli to Gorakhpur section of NH 29E, executed for MORTH through UP PWD.”
Arbitration award not yet in revenue; booked only on realisation
T. R. Rao · Q&A · p. 7
Arbitration award not yet in revenue; booked only on realisation
“See, only upon realization of amount we consider into the revenue.”
H1 revenue of Rs 2,664 crore includes Rs 217 crore arbitration award
T. R. Rao · Q&A · p. 11
H1 revenue of Rs 2,664 crore includes Rs 217 crore arbitration award
“So what we achieved, INR2,664 crores we achieved during the H1, so that includes INR217 crores of arbitration award we”
Risks
BESS: NHPC could not sign power sale agreement with DISCOM for BESS project
T. R. Rao · p. 8
BESS: NHPC could not sign power sale agreement with DISCOM for BESS project
“But however, NHPC could not sign the PSA, power sale agreement with the DISCOM.”
Delhi High Court stayed NHAI debarment orders against company and Awadh Expressway
Yogesh Jain · Managing Director · p. 4
Delhi High Court stayed NHAI debarment orders against company and Awadh Expressway
“On October 12, 2026, the Hon’ble Delhi High Court granted a stay on the effect of the debarment orders issued by the NHAI against both the Company and the Concessionaire, Awadh Expressway Pvt Ltd.”
Next hearing on the debarment case is on 26th November
T. R. Rao · p. 18
Next hearing on the debarment case is on 26th November
“See, we got the stay. Se, next date of hearing is on 26th of November.”
NHAI imposed no penalty or toll-loss recovery on Awadh Expressway; nothing booked in Q2
T. R. Rao · Q&A · p. 17
NHAI imposed no penalty or toll-loss recovery on Awadh Expressway; nothing booked in Q2
“So NHAI has not imposed any penalty, and also there is no recovery made for the toll loss. So, in quarter 2, we have not booked anything.”
Coal mining: Coal mining hit by local resistance to vacating land; now improving
T. R. Rao · p. 10
Coal mining: Coal mining hit by local resistance to vacating land; now improving
“With regard to coal mining, there are initial hiccups because of the severe resistance by the locals in vacating the land and encumbrances and encroachments are there but there also now things are getting improved.”
Other
First half revenue is usually lower than second half due to monsoon
T. R. Rao · p. 11
First half revenue is usually lower than second half due to monsoon
“First half of the any financial year will be less than the second half because of the monsoon and other kind of thing.”
HAM: Total equity requirement for 14 HAM projects is Rs 2,125 crore
Yogesh Jain · Managing Director · p. 5
HAM: Total equity requirement for 14 HAM projects is Rs 2,125 crore
“Total equity investment requirement for the 14 HAM projects, is Rs. 2,125 crore”
HAM: Rs 1,212 crore HAM equity infused; Rs 913 crore due over next two to three years
Yogesh Jain · Managing Director · p. 5
HAM: Rs 1,212 crore HAM equity infused; Rs 913 crore due over next two to three years
“Till September 2026, Company infused Rs. 1,212 crores and the remaining equity of Rs. 913.0 crores to be invested over the next two to three years.”
HAM: HAM equity of Rs 460 crore targeted for FY28
Pankaj Agarwal · Vice President · Q&A · p. 8
HAM: HAM equity of Rs 460 crore targeted for FY28
“We’re targeting for '28 is INR460 crores and the balance in the financial year '28-'29.”
Spare Rs 2,000 crore cash to fund equity in new projects if won
T. R. Rao · p. 19
Spare Rs 2,000 crore cash to fund equity in new projects if won
“then there will be a fresh equity requirement in these projects, and the remaining INR2,000 crores that is available, then we utilize this for the equity purpose.”
Sources
- Earnings call transcript, Q2 FY27 Filed 3 Nov 2026 · 21 pages
Management's own statements, quoted from its NSE filings. This page was read by AI and can contain mistakes: check the source pages before relying on any figure. No forecast or opinion of ours. Not investment advice.