NHPC

Q2 FY27 earnings and concall highlights

Price as of 16 Nov 2026
75.05−1.03%

Q2 FY27 earnings call · Guided by management

Call held 5 Nov 2026 · Read the filing on NSEFiling

₹2,400​CrAnnual revenue (AFC) · Parbati-II · normal levelRoy · p. 12
₹5,500​CrAnnual fixed charge · Subansiri Lower · yearly, full commissioningRoy · p. 13
₹10,000​CrEBITDARoy · p. 20
₹30,072​CrAnticipated project cost · Subansiri LowerGupta · p. 4
M.Cap
₹75,388Cr
P/E
17.4×
1Y return
−6.54%
From 52W high
−13.6%

Highlights are read by AI from the company's filing and can contain mistakes. Check the source page linked to each line.

Share price

Results Q2 FY27, as filed · consolidated · ₹ Cr

Q2 FY27Q2 FY26YoYQ1 FY27QoQ
Revenue4,4833,365+33.2%3,808+17.7%
EBITDA2,8762,027+41.9%2,352+22.3%
EBITDA margin64.2%60.2%+392 bps61.8%+239 bps
PBTProfit before tax1,8971,572+20.6%1,298+46.1%
Net profit1,5491,021+51.7%1,096+41.4%
EPS (₹)1.541.02+51.0%1.09+41.3%

From the company's own results filing on NSE. Net profit is the owners' share. Growth and the dotted lines are worked out from the filed figures.

Guidance

Revenue · Parbati-II · long termRs 2,400 CrParbati-II expected revenue about Rs 2,400 crore at tariff around Rs 8.50/unit
Revenue · Subansiri Lower · long termRs 5,500 CrSubansiri expected AFC about Rs 5,500 crore a year at full commissioning
EBITDA · long termRs 10,000 CrEBITDA expected to reach about Rs 10,000 crore after Subansiri, Pakal Dul commissioning
Net profit · FY28Rs 6,000-6,400 CrFY28 PAT targeted at Rs 6,000-6,400 crore
Net profit · Parbati-II · long termRs 680 CrParbati-II expected PAT about Rs 680 crore at 17% return on equity
Net profit · Subansiri Lower · long termRs 1,500-1,600 CrSubansiri expected PAT about Rs 1,500-1,600 crore
CapexRs 30,072 CrSubansiri cost Rs 30,072 crore, Rs 26,936 crore spent; no further cost rise expected
CapexRs 31,876 CrDibang cost Rs 31,876 crore incl Rs 6,716 crore grant; Rs 5,504 crore spent
Capex · FY30Rs 2,709 CrUri-I Stage-II: cost Rs 2,709 crore, Rs 33 crore spent, due November 2029
Capex · FY30Rs 2,994 CrDulhasti Stage-II: Rs 122 crore spent of Rs 2,994 crore, due November 2029
Capex · FY27Rs 2,057 CrRangit-IV: Rs 1,916 crore spent of Rs 2,057 crore, commissioning by December 2026
Capex · FY28Rs 12,728 CrPakal Dul: Rs 10,183 crore spent of Rs 12,728 crore; full commissioning by June 2027
Capex · FY29Rs 4,526 CrKwar: 42% progress, Rs 2,079 crore spent of Rs 4,526 crore, due May 2028
CapexRs 26,070 CrCCEA approved Rs 26,070 crore investment for Kamala HEP (1,720 MW)
Capex · FY28Rs 14,000-15,000 CrCapex of about Rs 14,000-15,000 crore a year from next year, consolidated
Capex · long termRs 1,11,000 Cr10-year capex plan about Rs 1,11,000 crore, needing Rs 40,000 crore equity
CapexRs 5,200 CrIndira Sagar-Omkareshwar PSP cost about Rs 5,200 crore

Operating cash generation put at about Rs 10,000 crore

Saroj Kumar Roy · p. 22
“So, total cash would be likely to be generated to the extent of Rs. 10,000 Crore approx., for example.”

More figures from the call

Company · Guidance
₹3,000–3,500​CrDepreciation · FY’28
“If you take conservative number of Rs. 6,000 Crore only, we will have depreciation also to the extent of Rs. 3,000 Crore – Rs. 3,500 Crore approx.”
Saroj Kumar Royp. 22
Teesta-V · Guidance
₹100–150​CrProfit · H2
“And similar kind of profit in H2 also to the extent of Rs. 100 Crore - Rs. 150 Crore odd, you can expect.”
Saroj Kumar Royp. 23
Company · Capex
₹5,232​CrCapex · H1
“CAPEX during H1 FY’26 is Rs. 5,232 Crore as against Rs. 5,683 Crore in the corresponding period of previous year on consolidated basis.”
Mahesh Kumar Sharma · Director (Finance)p. 11
Subansiri Lower · Capacity
1,250​MWCapacity commissioned
“In respect of our Subansiri Lower Project, which is 2,000 MW, we have already commissioned 5 units of 250 MW each i.e. totalling to 1,250 MW out of eight units.”
Bhupender Gupta · Chairman and Managing Directorp. 4
Subansiri Lower · Capacity
2​unitsUnits to be commissioned · current financial year
“Further, we are targeting to commission 2 more units of Subansiri during the current financial year and the remaining 1 unit is expected to be commissioned by June’27.”
Bhupender Gupta · Chairman and Managing Directorp. 4

In short

  1. 01Q2 FY27 PAT was Rs 1,549 crore, up 52%; revenue Rs 4,482 crore, up 33%.
  2. 02Q2 included a Rs 231 crore provision for Teesta-IV; adjusted PAT about 90% higher on standalone basis.
  3. 03Subansiri Lower: 5 of 8 units (1,250 MW) running; 2 more this year, last by June 2027.
  4. 04Subansiri expected AFC about Rs 5,500 crore a year and PAT Rs 1,500-1,600 crore at full commissioning.
  5. 05FY28 PAT targeted at Rs 6,000-6,400 crore; EBITDA expected to reach about Rs 10,000 crore.
  6. 06FY27 capex target Rs 14,300 crore; about Rs 14,000-15,000 crore a year from next year.
  7. 071,744 MW to be commissioned this year, then 1,250 MW in FY28, 1,390 MW in FY29, 1,000 MW in FY30.
  8. 08No fresh equity needed: internal resources cover equity for Rs 1,11,000 crore 10-year capex.

Capex

Teesta-VI HEP: Teesta-VI: 74% physical progress, estimated cost Rs 9,167 crore

Bhupender Gupta · Chairman and Managing Director · p. 4
“But we are sure that whatever the timeline we have now kept for completion of this project, we will achieve that because 74% physical progress has already been achieved. The estimated cost of this project is Rs. 9,167 Crore”

Teesta-VI HEP: Teesta-VI: Rs 5,650 crore spent; commissioning expected September 2029

Bhupender Gupta · Chairman and Managing Director · p. 5
“Rs. 5,650 Crore has already been spent till September’26 i.e. 62% of the estimated cost. The expected commissioning of the project is September’29.”

Kiru HEP: Kiru (624 MW): 92% progress, Rs 4,105 crore spent of Rs 5,409 crore

Bhupender Gupta · Chairman and Managing Director · p. 6
“In respect of Kiru HEP which is 624 MW, Overall 92% physical progress of project has been achieved and against the total estimated cost of Rs. 5,409 Crore, we have spent Rs. 4,105 Crore till September’26 which is 76% of the estimated cost.”

Ratle HEP: Ratle: 33% progress, Rs 1,749 crore spent of Rs 5,282 crore

Bhupender Gupta · Chairman and Managing Director · p. 6
“Overall, 33% physical progress has been achieved. The estimated cost of project is Rs. 5,282 Crore and we have spent Rs. 1,749 Crore till September’26.”

Pumped storage: Site work on at least two PSPs hoped to start next year

2​projects
Bhupender Gupta · Chairman and Managing Director · p. 7
“We are hopeful that next year, for at least two of the PSPs, physical work will be started at site.”

Capacity

Solar: 300 MW Bikaner solar commissioned of 1,000 MW CPSU scheme

Bhupender Gupta · Chairman and Managing Director · p. 7
“In respect of 1,000 MW capacity solar power projects allotted under CPSU scheme, we have already commissioned 300 MW Project in Bikaner, Rajasthan.”

Solar: 40 MW Ganjam solar and 50 MW Kerala floating solar expected by March 2027

Bhupender Gupta · Chairman and Managing Director · p. 7
“Our other under construction solar projects like 40 MW Solar Power Project in Ganjam, Odisha and one 50 MW Floating Solar Project in Kerala are also expected to be completed by March’27.”

Solar: Two 200 MW Khavada solar projects due December 2026 and September 2027

Bhupender Gupta · Chairman and Managing Director · p. 7
“Further, two projects of 200 MW each Grid-Connected Solar Photovoltaic Power Projects which are located in Gujarat State Electricity Corporation Limited’s RE Park at Khavada, Gujarat (Stage-I & Stage-III) are expected to be commissioned by December’26 and September’27 respectively.”

Pumped storage: 18 GW of pumped storage projects at DPR/PFR stage

Bhupender Gupta · Chairman and Managing Director · p. 7
“Currently, we have 18 GW PSPs, which are in the DPR/PFR stage.”

Renewable energy: 1,190 MW RE under construction, to be fully completed next year; delayed by connectivity

Bhupender Gupta · Chairman and Managing Director · p. 17
“And if you see as of now that 1,190 MW capacity is under construction and this will be 100% completed next year as I told, because these commissioning has been delayed due to the availability of the connectivity.”

Order book

Dibang Multipurpose Project: Dibang major contracts awarded; only small hydro-mechanical packages pending

Bhupender Gupta · Chairman and Managing Director · p. 15
“Only small contracts of HM (Hydro-Mechanical) are pending, because we always award as per the requirement at the site.”

Renewable Energy Implementing Agency: As REIA, tendered about 23,120 MW, awarded 73 projects, PPAs signed for 9,000 MW

Bhupender Gupta · Chairman and Managing Director · p. 18
“We have tendered out in NHPC around 23,120 MW of the bids. Out of that, we have awarded 73 projects. PPA has been signed only for 9,000 MW.”

Renewable Energy Implementing Agency: Another 5,000-7,070 MW of REIA PPAs expected, total around 15,000

Bhupender Gupta · Chairman and Managing Director · p. 18
“Also, we are expecting that around 5,000 - 7,070 MW will also be signed, totalling to around 15,000.”

Segments

Subansiri Lower: Full Subansiri impact largely in FY28, full top line from FY29

Saroj Kumar Roy · p. 13
“Since last unit of Subansiri is spilling over in next financial year, the full impact of Subansiri would be largely in FY’28 and then FY’29 onwards, you will be having full top line, then the expected PAT also.”

Teesta-V: Teesta-V Q2: 859 MUs, top line Rs 150-160 crore, PBT Rs 99 crore

Saroj Kumar Roy · p. 13
“During Q2, Teesta-V has generated 859 MUs. The top line we have from Teesta-V is around Rs. 150 - 160 Crore. If you strike off all expenses, then the PBT contributed by Teesta-V is Rs. 100 Crore, more precisely Rs. 99 Crore.”

Subansiri Lower: Subansiri added Rs 132 crore profit in Q2, Rs 170 crore in H1, on extra generation

Saroj Kumar Roy · p. 14
“That is the reason Subansiri Lower has generated around 300 MUs higher than the proportionate design energy of four units and this 300 MU is adding incremental PAT. Subansiri has added Rs. 132 Crore approx. profit in Q2 and almost Rs. 170 Crore approx. profit in H1.”

Renewable energy: States seeking JVs for solar, solar plus BESS and wind; plan to expand RE

Bhupender Gupta · Chairman and Managing Director · p. 17
“So, they are in touch with us to have a JV and construct the solar plant or solar plus BESS or also the wind projects also in their state. We are planning to expand our RE in the future.”

Renewable energy: Will not build RE projects without a PPA in place

Bhupender Gupta · Chairman and Managing Director · p. 18
“We don't want to construct the projects and then we are not having any PPA. That we do not want to do.”

Demand

About 70% of generation typically in H1 and 30% in H2

Saroj Kumar Roy · p. 23
“Basically, you see typically 70% generation if you take average of last five years, the actual numbers I am sharing with you, 70% generation happens in H1 and 30% in H2.”

Power shortfall now in morning and evening peak hours

Bhupender Gupta · Chairman and Managing Director · p. 17
“The problem now is that we have shortfall in the peaking hours i.e. in the evening as well in the morning also.”

States' energy requirement and pattern changed sharply in the past year

Bhupender Gupta · Chairman and Managing Director · p. 18
“Earlier they were having a very clear-cut adequacy plan, but we have seen in the past one year the energy requirement, energy pattern has changed drastically in all the states.”

Q2 is the peak generation period; Q3 and Q4 are lean

Saroj Kumar Roy · p. 23
“You have now nine months only and the peak period is only Q2. The Q3, Q4 is the lean period.”

Margins and costs

H1 finance cost rose to Rs 1,162 crore from Rs 539 crore on Subansiri loan interest

Mahesh Kumar Sharma · Director (Finance) · p. 9
“During Half Year FY’27, there has been increase in the Finance Cost from Rs. 539 Crore to Rs. 1,162 Crore means by Rs. 623 Crore, which is mainly due to increase on account of interest on loan related to Subansiri Lower Project charged to P&L since its part commissioning.”

H1 depreciation up to Rs 1,210 crore from Rs 877 crore on Subansiri part commissioning

Mahesh Kumar Sharma · Director (Finance) · p. 9
“During Half Year FY’27, the Depreciation & Amortization Expenses have gone up from Rs. 877 Crore to Rs. 1,210 Crore means by Rs. 333 Crore which is mainly due to part commissioning of Subansiri Lower Project.”

H1 generation expenses down to Rs 552 crore on lower water cess, Uttarakhand court verdict

Mahesh Kumar Sharma · Director (Finance) · p. 9
“During Half Year FY’27, the Generation Expenses have come down from Rs. 592 Crore to Rs. 552 Crore means by Rs. 40 Crore, which is due to lower water cess on account of lower generation in the power stations situated in U.T. of J&K and no water cess for power station situated in Uttarakhand in view of verdict of Hon’ble High Court of Uttarakhand in favor of NHPC.”

Q2 employee expenses up to Rs 392 crore from Rs 326 crore

Mahesh Kumar Sharma · Director (Finance) · p. 9
“During Q2 FY’27, the Employee Benefit Expenses has gone up from Rs. 326 Crore to Rs. 392 Crore means by Rs. 66 Crore which is mainly due to part commissioning of Subansiri Lower Project by Rs. 19 Crore and increase on account of promotion, DA and other factors by Rs. 47 Crore.”

H1 incentives Rs 103 crore against Rs 265 crore, down 47%

Mahesh Kumar Sharma · Director (Finance) · p. 10
“So, total incentives in the First Half Year FY’27 is Rs. 103 Crore as against Rs. 265 Crore in the corresponding previous period. That is a decrease of Rs. 162 Crore and in percentage terms, it is 47%.”

Debt and working capital

H1 collections from beneficiaries Rs 5,126 crore against Rs 4,764 crore

Mahesh Kumar Sharma · Director (Finance) · p. 11
“On realization front, NHPC has received Rs. 5,126 Crore from the beneficiaries against sale of energy during Half Year FY’27 as compared to Rs. 4,764 Crore in the corresponding period of previous year.”

Trade receivables Rs 4,283 crore at Sept 2026; net due Rs 1,893 crore, Rs 290 crore over 45 days

Mahesh Kumar Sharma · Director (Finance) · p. 11
“Reported trade receivables Rs. 4,283 Crore, less unbilled debtors Rs. 1,573 Crore, billed receivables after netting off is Rs. 2,710 Crore, less debtors dues which have been converted to instalments as per CERC Tariff Orders and other orders Rs. 817 Crore, so net amount due is Rs. 1,893 Crore and dues more than 45 days is Rs. 290 Crore.”

Receivables were Rs 1,159 crore on 3 November; only Rs 6 crore over 45 days

Saroj Kumar Roy · p. 19
“If you look at today's number, I mean, yesterday, what receivables we had, the total receivable was Rs. 1159 Crore only and more than 45 days, it was only Rs. 6 Crore.”

Average debtor turnover is 51 days

Saroj Kumar Roy · p. 19
“Since our average debtor turnover days is only 51 days only, so all receivables are coming absolutely in time and there is no issue from the receivable fronts.”

Parbati-II: Parbati-II interim order received; 75% billing being done

Saroj Kumar Roy · p. 20
“Parbati-II, we have already received interim order, so 75% billing is being done.”

Fund raising

About Rs 4,000 crore yearly equity need to be met from internal resources

Saroj Kumar Roy · p. 22
“On an average, Rs. 4,000 Crore approx. yearly equity is required from NHPC side. Our internal resources is sufficiently taking care of any equity requirement from the capex perspective.”

Acquisitions and new business

Jalpower Corporation Limited: Merger of JPCL with NHPC in process; Second Motion Application filed

Bhupender Gupta · Chairman and Managing Director · p. 5
“Further, the merger of JPCL with NHPC is in process and Second Motion Application has already been filed with the Ministry of Corporate Affairs.”

Kamala HEP: Kamala to be built via JV with Arunachal Pradesh; subsidiary formation in process

Bhupender Gupta · Chairman and Managing Director · p. 6
“The project will be implemented through JV between NHPC and Government of Arunachal Pradesh. The formation of subsidiary is in process.”

Etalin: Etalin transfer consideration to SJVN not yet paid; due after PIB approval

Bhupender Gupta · Chairman and Managing Director · p. 16
“No, that amount is not paid yet. It will be paid once PIB happens for the Etalin.”

NHPC Green Energy: No decision on hiving off solar business until projects are commissioned

Bhupender Gupta · Chairman and Managing Director · p. 17
“We are not going to do anything till commissioning as of now. After commissioning, we will see what to do.”

Etalin: Etalin transfer already approved by SJVN and NHPC boards

Bhupender Gupta · Chairman and Managing Director · p. 17
“But principally, it is already decided and it is approved by the Board of SJVN as well as by the NHPC Board.”

Dividends and buybacks

Total FY26 dividend Rs 1.61 per share, final Rs 0.21 paid in September 2026

Mahesh Kumar Sharma · Director (Finance) · p. 11
“The company has paid final dividend at the rate of 2.10% i.e. Rs. 0.21 per equity share for the financial year 2025-2026 in the month of September’26, which is in addition to interim dividend at the rate of 14.00% i.e. Rs. 1.40 per equity share, resulting in total dividend at the rate of 16.10% i.e. Rs. 1.61 per equity share”

Dividend on average 4% of net worth, roughly Rs 1,800 crore

Saroj Kumar Roy · p. 22
“On an average, we pay 4% of net worth as dividend. If you consider Rs. 42,000 Crore approx. net worth and going forward, if you consider Rs.45,000 Crore net worth, the 4% of the same is roughly Rs. 1,800 Crore.”

One-offs

Q2 other expenses include Rs 231 crore provision for Teesta-IV project

Mahesh Kumar Sharma · Director (Finance) · p. 10
“This is mainly due to the increase in expenses related to Subansiri Lower Project by Rs. 92 Crore and Provision related to Teesta-IV Project of Rs. 231 Crore which is offset by decrease in insurance premium of other power stations by Rs. 52 Crore.”

H1 other income down 31% to Rs 338 crore; prior year had insurance claim income

Mahesh Kumar Sharma · Director (Finance) · p. 8
“Other Income for Half Year FY’27 is of the order of Rs. 338 Crore in comparison to Rs. 494 Crore during the corresponding previous period, which is about 31% lower or by Rs. 156 Crore. This is mainly due to income from insurance claim in the corresponding previous period.”

Adjusted Q2 PAT, adding back Teesta-IV provision, 90% higher year on year (standalone)

Saroj Kumar Roy · p. 14
“adjustment you have to make in adjusted PAT and if you calculate the adjusted PAT, so that will be 90% higher than the corresponding quarter, against the 65% which we have shared. These are on standalone basis.”

Q2 other income Rs 187 crore against Rs 265 crore a year earlier

Mahesh Kumar Sharma · Director (Finance) · p. 8
“Other Income for Q2 FY’27 is of the order of Rs. 187 Crore in comparison to Rs. 265 Crore during the corresponding previous period”

Risks

Teesta-VI HEP: Teesta-VI (500 MW): tunnel is the only hurdle

Bhupender Gupta · Chairman and Managing Director · p. 4
“In respect of Teesta-VI HEP (500 MW), the work is progressing well and the only hurdle which we are facing there is the tunnel.”

Solar: 100 MW AP and 600 MW Gujarat solar delayed to Jan 2027 and Nov 2027 on connectivity

Bhupender Gupta · Chairman and Managing Director · p. 7
“Further, 100 MW Project in Andhra Pradesh and 600 MW Project in Gujarat are expected to be commissioned by January’27 and November’27 respectively. There is some issue of connectivity that's why these projects are getting delayed.”

Parbati-II: Parbati-II tariff hearing on 11 November; expected to be the final hearing

Mahesh Kumar Sharma · Director (Finance) · p. 12
“The next hearing of Parbati-II has been fixed on 11 November. We hope that this will be the final hearing and thereafter, order will be reserved.”

Subansiri Lower: Subansiri interim tariff order reserved; expected very soon

Mahesh Kumar Sharma · Director (Finance) · p. 13
“As far as hearing is concerned, the hearing has been over and the order is now reserved for interim tariff. Therefore, we are expecting the interim tariff very soon in respect of Subansiri Lower Project.”

Sawalkot: Sawalkot CCEA approval timing uncertain, not in company's hands

Bhupender Gupta · Chairman and Managing Director · p. 15
“If we get the CCEA approval by December but we are not sure yet because that is not in our hand. Ultimately, Government has to give the approval.”

Other

H1 FY27 generation 23,741 MUs, up 14% from 20,866 MUs

Bhupender Gupta · Chairman and Managing Director · p. 3
“During the Half Year FY’27, our power stations have achieved generation of 23,741 MUs as against 20,866 MUs generated in corresponding period of the previous year, which is higher by 14% or 2,875 MUs.”

Q2 FY27 generation 13,935 MUs, up about 17% from 11,870 MUs

Mahesh Kumar Sharma · Director (Finance) · p. 8
“our power stations have achieved generation of 13,935 MUs as against 11,870 MUs generated in the corresponding period of the previous year which is higher by about 17% or 2,065 MUs.”

H1 FY27 plant availability factor 86.67% against 81.10% a year earlier

Bhupender Gupta · Chairman and Managing Director · p. 4
“Our PAF for Half Year FY’27 stands at 86.67% against the corresponding previous period PAF of 81.10%, which is about 6% higher.”

Q2 FY27 plant availability factor 92.24% against 78.58% a year earlier

Mahesh Kumar Sharma · Director (Finance) · p. 8
“Our PAF for 2 Quarter FY’27 stands at 92.24% against the corresponding previous period PAF of 78.58% which is about 14% higher.”

Q2 FY27 revenue from operations Rs 4,482 crore, up about 33%

Mahesh Kumar Sharma · Director (Finance) · p. 8
“During Q2 FY’27, Company has earned Revenue from Operation of Rs. 4,482 Crore as against Rs. 3,365 Crore in the corresponding previous period which is about 33% higher or by Rs. 1,117 Crore.”

Sources

Management's own statements, quoted from its NSE filings. This page was read by AI and can contain mistakes: check the source pages before relying on any figure. No forecast or opinion of ours. Not investment advice.