Metals & Mining · NSE: NATIONALUM

National Aluminium Company

Price as of 12 Nov 2026
333.10+2.18%

Q2 FY27 earnings call · Guided by management

Call held 3 Nov 2026 · Read the filing on NSEFiling

4.8​million tonnesCaptive coal production · Captive coal · this yearSingh · p. 4
₹500–1,000​/tonneAlumina cost reduction · Alumina · H2 FY27Behuria · p. 6
₹150​CrPBT addition from new refinery · Alumina refinery · H2 FY27Singh · p. 8
₹100​CrProfit addition from techno-economics · H2 FY27Singh · p. 8
M.Cap
₹61,178Cr
P/E
8.5×
1Y return
+24.78%
From 52W high
−25.2%

Highlights are read by AI from the company's filing and can contain mistakes. Check the source page linked to each line.

Share price

Results Q2 FY27, as filed · consolidated · ₹ Cr

Q2 FY27Q2 FY26YoYQ1 FY27QoQ
Revenue5,4194,292+26.3%5,302+2.2%
EBITDA2,4111,926+25.2%2,708-11.0%
EBITDA margin44.5%44.9%-39 bps51.1%-658 bps
PBTProfit before tax2,4711,895+30.4%2,689-8.1%
Net profit1,8351,430+28.3%2,003-8.4%
EPS (₹)9.997.79+28.2%10.91-8.4%

From the company's own results filing on NSE. Net profit is the owners' share. Growth and the dotted lines are worked out from the filed figures. In Q2 FY27 the filing tags the owners' profit as ₹0 Cr against its own period profit; the period profit less minority interest is shown.

Guidance

Capex90-92%Refinery critical-path packages at 90-92% physical completion
Capex1-3 monthsBrownfield smelter running one to three months behind timelines given to Ministry of Mines
CapexRs 25,000 CrSmelter and power plant together to cost around Rs 25,000 crore
Capex18 km18 km Pottangi conveyor targeted in 2 to 2.5 years
Capex · FY27Rs 1,800 CrFY27 capex plan around Rs 1,800 crore; about Rs 800 crore spent in H1

Margins expected to be stable in the second half

Brijendra Pratap Singh · Chairman · Q&A · p. 8
“In the second half of this fiscal, we expect that our margin would be stable”

Same margin level expected for next 3-4 years until new smelter commissioned

Abhay Kumar Behuria · Director (Finance) · p. 22
“will be maintaining the same margin level in the next 3, 4 years, and till our new smelter is commissioned.”

More figures from the call

Alumina · Guidance
₹35,000​/tonneAverage alumina realisation · H2 FY27
“If you see the relation, if you see the H1 realization, average realization was INR33,200, and we are expecting that in our H2, average realization will be around INR35,000.”
Brijendra Pratap Singh · Chairmanp. 7
Company · Guidance
₹300–350​CrExtra profit in H2 · H2 FY27
“we are going to get 300to 350 extra in the next half of this year.”
Brijendra Pratap Singh · Chairmanp. 8
Alumina · Guidance
7​kgCaustic soda consumption cut · next six months
“We are targeting to reduce caustic soda consumption by 7 kg at least in the next six months.”
Managementp. 15
Alumina · Guidance
2.3​million tonnesAlumina production rate from four existing streams · FY27
“You see, now with the present family of four streams, we are going at the rate of 2.3 and 0.2. We are planning from 5th Stream.”
Brijendra Pratap Singh · Chairman · Q&Ap. 8
Alumina · Guidance
6–7​kgCaustic soda consumption reduction · H2 FY27
“That actually will be taken, and that will be reduced to 6 kg to 7 kg in caustic soda process.”
Abhay Kumar Behuria · Director (Finance)p. 7
Alumina · Guidance
₹400–500​/tonneAlumina cost reduction · H2 FY27
“Rather, we'll be reducing cost by INR500 or INR400. That is your target.”
Brijendra Pratap Singh · Chairmanp. 7

In short

  1. 01H1 FY27 revenue was Rs 11,143 crore, EBITDA Rs 5,539 crore and PAT Rs 3,837 crore, all record highs.
  2. 025th Stream refinery production is planned from the last week of December or early January; about 0.75-0.8 million tonnes expected next year.
  3. 03Brownfield smelter (about Rs 17,000-18,000 crore) targets mechanical completion by December 2030; smelter plus power plant cost about Rs 25,000 crore.
  4. 04FY27 capex plan is about Rs 1,800 crore, with Rs 800 crore spent in H1; year-end cash expected at Rs 12,000 crore.
  5. 05H2 alumina realisation expected around Rs 35,000 per tonne versus Rs 33,200 in H1; export prices seen at $370-380.
  6. 06Management expects H2 margins to be stable and costs not to rise above H1 levels.
  7. 07Alumina exports fell to one vessel in October due to Strait of Hormuz restrictions; six vessels planned for November.
  8. 08Pottangi mine start is held up by tree-felling and land issues, which management hopes to solve in 2-3 months.

Capex

Smelter expansion: Brownfield smelter investment around Rs 17,000-18,000 crore

Brijendra Pratap Singh · Chairman · p. 5
“There will be around INR17,000 crores or INR18,000 crores of investment.”

Smelter expansion: Main smelter capex to start from FY28-29; Rs 200-300 crore earlier for technology licence

Brijendra Pratap Singh · Chairman · p. 5
“will start coming from the financial year '28-'29 when the actual groundwork. Some ordering of technology license, which we have signed, some capex very less around INR200 crores, INR300 crores will come.”

Smelter expansion and power plant: Smelter and power plant capex of Rs 5,000-6,000 crore, later Rs 7,000-8,000 crore

Brijendra Pratap Singh · Chairman · p. 6
“So around in the year '27, '28, '29 around, I think INR5,000 crores, INR6,000 crores or maybe after that the INR7,000 crores INR8,000 crores will come in '28-'29,”

Alumina refinery: Red mud filtration unit to cost around Rs 400-500 crore

Brijendra Pratap Singh · Chairman · p. 18
“We are going for a red mud filtration unit, for which around we are spending around INR400 crores to INR500 crores.”

Pottangi mines: Long-distance conveyor investment only Rs 1,000 crore

Abhay Kumar Behuria · Director (Finance) · p. 19
“with the long-distance conveyor, that -- for that, we are investing only INR1,000 crores.”

Capacity

Alumina refinery: 5th Stream refinery to take three to five months to reach 100% of rated capacity

3–5​months
Brijendra Pratap Singh · Chairman · Q&A · p. 4
“four months or maybe five months -- three, four, five months to reach to the 100% of the rated”

Segments

Alumina exports: Six vessels planned in November; about four vessels a month expected after

6​vessels
Brijendra Pratap Singh · Chairman · p. 12
“we are planning around six vessels dispatch in this month. So, it is getting normalized, and what we are hoping is in the coming days and times, we'll be dispatching around four vessels every month.”

Alumina: Alumina prices expected around $370 to $380 on average

Brijendra Pratap Singh · Chairman · p. 12
“The prices will be somewhere around $370 to $380 average what we are expecting depending on the demand supply situation.”

Alumina: EOI floated for 2-3 year alumina supply tie-ups with Middle East smelters

Brijendra Pratap Singh · Chairman · p. 12
“we have already earlier floated one EOI for a long-term tie up with the smelters in the Middle East and other places, maybe 2 years or 3 years tie up”

Alumina: About 2 million tonnes excess alumina until smelter ramp-up in 2031 or 2032

Brijendra Pratap Singh · Chairman · p. 12
“Year '31 or '32, the final total ramp up will be there. So till then, we'll be having an excess of around 2 million tonnes of alumina with us.”

Alumina: Bulk domestic alumina sales being explored with import-parity pricing finalised

Abhay Kumar Behuria · Director (Finance) · p. 12
“we are also exploring the selling alumina in the domestic market also in the bulk quantity that we have already finalized a pricing mechanism, and that will be in import quality basis.”

Demand

Alumina: Alumina prices rose on refinery issues in China, at Rusal and in Australia

Brijendra Pratap Singh · Chairman · p. 7
“So, there is an increase in alumina spot prices realization because some of the refineries issues in China, in Rusal, in Australia also, which has led to increase on these prices of alumina.”

Alumina: Alumina price seen at 370-400 as Middle East smelters start

Brijendra Pratap Singh · Chairman · p. 7
“We will be getting somewhere around 370 to 400 because some of the smelters are starting in Middle East.”

Alumina: Projections showed about 1.6 million tonnes of excess global alumina in FY27

Brijendra Pratap Singh · Chairman · p. 7
“the projections were that in the year '26-'27 financial year, around 1.6 million ton of excess alumina will be there in the global market.”

Alumina: Alumina seen at 12.5-13% of LME aluminium, not 15-16%

Abhay Kumar Behuria · Director (Finance) · Q&A · p. 19
“It will not go to 15% or 16%, but it will be certainly at the level of 13% or 12.5%.”

Alumina: Indonesia smelters of 0.5-0.6 million tonnes to be commissioned in next one to two years

Abhay Kumar Behuria · Director (Finance) · p. 22
“The smelters around 0.5 million ton to I think, 0.6 million ton of capacity smelters are going to be commissioned in maybe next year or next to next year.”

Margins and costs

Power plant: Coal from Neyveli JV to come at their production cost with no premium

Brijendra Pratap Singh · Chairman · p. 5
“So, we'll be sourcing coal from there, and the coal which we'll be getting will be at their production cost and no premium they will be charging from us.”

Cost rise driven by caustic soda, CP coke and fuel oil

Brijendra Pratap Singh · Chairman · p. 6
“Increase has been in caustic soda, in CP coke, and in fuel oil. These are three areas, which the cost has increased”

Caustic soda at Rs 46,900 in H1; Q3 price seen around Rs 49,000

Brijendra Pratap Singh · Chairman · p. 6
“In H1 this year, the price went up to INR46,900, around INR4,700, INR4,800 increase. And Q3, the prices will be around INR49,000.”

CP coke rose from Rs 44,600 to Rs 63,700 in H1; Q3 projected at Rs 70,600

Brijendra Pratap Singh · Chairman · p. 6
“CP coke, you see in '25-'26, it was average CP coke was INR44,600. H1 this year, it went to INR63,700, and Q3 the projection is INR70,600.”

No major input cost increase expected in H2

Abhay Kumar Behuria · Director (Finance) · p. 6
“So, in the next H2, there is no major increase in the input cost. Rather, we'll be controlling our cost by improving our economic efficiency.”

Debt and working capital

Cash balance expected at Rs 12,000 crore at end of fiscal

Management · Q&A · p. 14
“Yes. We are expecting a cash balance at the end of this fiscal INR12,000 crores.”

Fund base rose from 8,500 to around 12,000, lifting interest income

Abhay Kumar Behuria · Director (Finance) · p. 10
“In our fund base, it was 8,500 people, that's around 12,000. And from that the interest earning has increased.”

Acquisitions and new business

Power plant: 50:50 power plant JV with Neyveli Lignite Corporation approved by DIPAM

Brijendra Pratap Singh · Chairman · p. 5
“we are making a JV company with Neyveli Lignite Corporation. Neyveli Lignite Corporation, 50% -- 50% JV company is already approved by DIPAM and all that.”

Dividends and buybacks

Aluminium: No commodity hedging under company policy

Abhay Kumar Behuria · Director (Finance) · p. 9
“Actually, as per NALCO policy, we have not gone for any hedging of our commodity.”

One-offs

Additional royalty taken in H1 on Odisha government claim will not repeat in H2

Brijendra Pratap Singh · Chairman · p. 8
“we have taken an additional impact of royalty, because the area which the government of Odisha has claimed that we have margin in the first half of the year, which will not be repeated in the second half.”

Risks

Pottangi mines: Pottangi mine start held up by tree clearing for access road, facing local resistance

Brijendra Pratap Singh · Chairman · p. 4
“But our one of the main constraints which we are facing is starting the mines is the clearing of the trees for the road making going from NH to mines.”

Alumina: Shipping blockages raised insurance and freight charges, lowering spot buyer bids

Brijendra Pratap Singh · Chairman · p. 8
“So, due to which the insurance charges have increased, the shipment charges have increased.”

Pottangi mines: Public hearing for Pottangi conveyor land was deferred

Brijendra Pratap Singh · Chairman · p. 10
“For that, public getting is scheduled, and it was scheduled in 27th of this month. Again, due to some issues, it is deferred.”

Alumina exports: Only one alumina vessel dispatched in October

Brijendra Pratap Singh · Chairman · p. 12
“We could only dispatch one vessel in October.”

Railway restrictions on rake supply cut coal deliveries to the refinery

Management · p. 13
“There is a restriction from railways for the supply of rigs to the integrated power plants.”

Other

H1 revenue Rs 11,143 crore, EBITDA Rs 5,539 crore, PBT Rs 5,160 crore, PAT Rs 3,837 crore, all record highs

Bharat Kumar Sahu · Company Secretary · p. 3
“In fact, the H1 revenue was all time high of INR11,143 crores, all time high of EBITDA of INR5,539 crores, highest ever PBT of INR5,160 crores, highest ever PAT of INR3,837 crores.”

Q2 net profit Rs 1,835 (crore), up 28% year on year

Bharat Kumar Sahu · Company Secretary · p. 3
“The Q2 net profit, of Rs.1,835 up by 28% year-on-year basis.”

Captive coal: Environmental clearance for 4.8 million tonnes coal expected within two or three months

Brijendra Pratap Singh · Chairman · p. 4
“Environmental clearance for 4.8 million is under process, and I think within two or three months,”

Pottangi mines: Pottangi land and tree-felling issues expected to be solved in 2-3 months

Brijendra Pratap Singh · Chairman · p. 10
“We are expecting that this -- all the issues we will be able to solve in the next 2 months to 3 months.”

Hedging to be reviewed after 5th Stream refinery is commissioned

Abhay Kumar Behuria · Director (Finance) · p. 9
“After commissioning of our 5th Stream refinery, we'll see that how we should go for any hedging or not.”

Sources

Management's own statements, quoted from its NSE filings. This page was read by AI and can contain mistakes: check the source pages before relying on any figure. No forecast or opinion of ours. Not investment advice.