3​GWRenewable capacity commissioning · Renewables · FY27Mahendra · p. 5
1​GWhEnergy storage commissioning · Energy storage · FY27Mahendra · p. 5
8.5​GWC&I installed capacity · C&I · by 2030Mahendra · p. 5
₹20,000​CrCapex · FY27Prabhakaran · Q&A · p. 16
M.Cap
₹95,277Cr
P/E
41.1×
1Y return
−1.59%
From 52W high
−15.8%

Highlights are read by AI from the company's filing and can contain mistakes. Check the source page linked to each line.

Share price

Results Q2 FY27, as filed · consolidated · ₹ Cr

Q2 FY27Q2 FY26YoYQ1 FY27QoQ
Revenue6,3685,177+23.0%5,207+22.3%
EBITDA3,6182,996+20.7%2,873+25.9%
EBITDA margin56.8%57.9%-108 bps55.2%+162 bps
PBTProfit before tax1,349954+41.4%694+94.4%
Net profit1,056705+49.9%471+124.3%
EPS (₹)5.624.04+39.1%2.57+118.7%

From the company's own results filing on NSE. Net profit is the owners' share. Growth and the dotted lines are worked out from the filed figures.

Guidance

Capex · FY27Rs 20,000 CrCapex guidance of about Rs 20,000 crore for FY27
Capex · Thermal - KSK Mahanadi3 yearsKSK infrastructure ready for 3.6 GW, supporting 3-year build
Capacity · FY3030 GWLocked-in pipeline gives line of sight to 30 GW target for 2030
Capacity · FY2716.70-16.80 GWOperational capacity of 16.7 to 16.8 GW expected by FY27 year-end
Capacity · Renewables · FY273 GW3 GW renewable commissioning target for FY27 reaffirmed, capex about Rs 20,000 crore
Capacity · Energy storage · FY271 GWhAbout 1 GWh of energy storage projects expected to be commissioned in FY27
Capacity · C&I8.50 GWC&I portfolio of 3.7 GW expected to grow to over 8.5 GW by 2030
Capacity · Thermal3,200 MWSalboni: turbine orders for all four 800 MW units placed; first unit expected by 2030
Capacity · Thermal - KSK Mahanadi · FY28600 MWKSK 600 MW fourth unit on track for FY28; balance 1,200 MW by FY29
Capacity · Renewables · long term2.50-3 GWRenewable capacity additions guided at 2.5 GW to 3 GW every year

Merchant: Q3 merchant capacity fully booked; pricing expected same or better than Q2

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 11
“Definitely, third quarter is fully booked. And maybe I'll not comment on the pricing, but the pricing discovered may be either same or better than this, not lower than these for quarter 3.”

More figures from the call

Company · Guidance
8.5​%Debt cost
“But we are closely working with the banks and others to kind of refinance some of this. And I think at this point in time, we'll kind of look at not more than 8.50% is what we can look at.”
C. Prabhakaran · Chief Financial Officer · Q&Ap. 15
Renewables · Capacity
1.4​GWRenewable capacity commissioned · FY27 to date
“Since April, we have commissioned 1.4 GW of organic renewable capacity as compared to last full year’s approximately 1.2 GW.”
Sharad Mahendra · Joint Managing Director and Chief Executive Officerp. 4
Renewables · Capacity
513​MWCapacity added in quarter · Q2 FY27
“In Q2, we added 513 MW, comprising 301 MW of solar and 212 MW of hybrid capacity.”
Sharad Mahendra · Joint Managing Director and Chief Executive Officerp. 4
Company · Capacity
15.1​GWInstalled capacity
“Including the 300 MW Maruti thermal acquisition, total capacity additions since April stand at 1.7 GW, taking our installed capacity above 15.1 GW, with renewables accounting for approximately 61% of the portfolio.”
Sharad Mahendra · Joint Managing Director and Chief Executive Officerp. 4

In short

  1. 01Management is confident of commissioning 3 GW of renewable capacity in FY27, with planned capex of about Rs 20,000 crore.
  2. 021.4 GW of organic renewable capacity has been commissioned since April; installed capacity is above 15.1 GW.
  3. 03Renewable additions are guided at 2.5 GW to 3 GW every year, and the 30 GW target for 2030 is reiterated.
  4. 04Q2 FY27 revenue was Rs 6,658 crore and PAT was Rs 1,141 crore.
  5. 05Q3 merchant capacity is fully booked at prices expected to be the same as or above Q2's Rs 6.9 per unit.
  6. 06Debt cost fell to 8.28%; management expects it to stay at or below 8.50% even if rates rise.
  7. 07The Maruti Clean Coal & Power acquisition closed at an EV of Rs 1,410 crore; the KSK expansion is due in FY28 and FY29.
  8. 08C&I capacity is expected to grow from 3.7 GW to over 8.5 GW by 2030.

Capex

Thermal - KSK Mahanadi: Mahanadi expansion capex per MW at least 25% to 30% below industry average

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 17
“the investment in Mahanadi expansion, doubling the capacity will be at least 25% to 30% lower cost per MW capex as compared to the industry average.”

Thermal: Boiler order for entire Salboni project placed with Durgapur facility

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 6
“We have placed the boiler order for the entire Salboni project with the Durgapur facility, which sits in the same state as the project.”

Wind manufacturing: Halol blade plant producing since June; Chitradurga facility on track for Q3 FY27

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 6
“Our Halol wind blade facility has been producing blades for our wind projects since its commissioning in June, and the Chitradurga facility remains on track for completion in Q3 FY27.”

Thermal - KSK Mahanadi: Mahanadi expansion: first unit expected in FY28, other two units in FY29

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 8
“the project work has started, as we have said that the first unit is expected to be commissioned in FY28 and balance two Units in FY29.”

Energy storage: Solar-plus-battery projects for evening discharge to start, using existing connectivity

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 11
“Now we are going to start the project work, wherein we will be setting a solar capacity for charging the batteries and only using our existing connectivity for solar, which we have got the sanction allocation for the evening discharge through the battery.”

Capacity

Pumped storage: Pumped storage pipeline of about 26.4 GWh on track

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 5
“Meanwhile, our sizeable pumped storage pipeline of about 26.4 GWh remains on track.”

Energy storage: Additional BESS capacity planned over and above the 3.2 GWh portfolio

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 11
“So we are also working on, and we will be definitely commissioning at this BESS capacity, as you said, all this is over and above that 3.2 GWh.”

Hydro: Tidong commissioned in Q1 FY27 ahead of October 2026 schedule; 199 MUs at 61% PLF in Q2

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 6
“Our Tidong plant, which was commissioned in Q1FY27 before the scheduled timeline of October 2026, gave us a healthy advantage of ongoing hydro season – the plant generated 199 MUs in Q2FY27 at a PLF of 61%.”

Renewables: Remaining 1.6 GW for FY27 has land, connectivity, equipment and long-term PPAs in place

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 5
“On the remaining 1.6 GW, we are fully on track. Land and transmission connectivity are secured, equipment is either on site or in transit, and offtake is backed by long-term PPAs.”

Energy storage: FY27 BESS projects are standalone, under ESAs, mainly in Rajasthan and Kerala

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 12
“this is all is the ESA capacity, which are going to be under the ESA. And these are majorly in two states, which is Rajasthan and the state of Kerala.”

Order book

Group captive: 4.5 GW of 6.2 GW Group MoUs not yet tied up; 2 GW in advanced discussion

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 5
“Of the 6.2 GW of MoUs signed with Group companies in Q2FY24, 4.5 GW is yet to be tied up, and 2 GW of this is under advanced discussion.”

Thermal: 30 GW target includes only 800 MW of 3.2 GW Salboni; 2.4 GW beyond it

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 12
“we have signed 3.2 GW of Power purchase agreement with the state of West Bengal and setting up a greenfield plant in Salboni. Out of that, 30 GW contains only 800 MW of phase I, balance all 2.4 GW is beyond 30.”

Renewables: All under-construction capacity is under PPAs with utilities, C&I and group captive

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 12
“project execution is all under PPA, which is basically with utilities, with C&I customers and group captive.”

Group captive: 2 GW of group captive under discussion said to be closing now

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 12
“But right now, it is all under a PPA, which is out of it 2 GW is under group captive which are under discussion and that is going to get closed now.”

Renewables: No capacity being set up for merchant sale so far

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 12
“We are not investing anything or setting up any capacity till now for a merchant”

Segments

Hydro: Hydro generation up 13% to 3,421 million units, from Kutehr and Tidong

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 6
“Overall, driven by incremental generation from Kutehr and Tidong, our hydro generation was 3,421 million units, up 13% year-on-year.”

Thermal: Thermal PLF 75% in Q2 vs All-India 67.8%

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 7
“Our consolidated thermal PLF was 75% in Q2, against the All-India thermal PLF of 67.8%.”

Thermal - Utkal: Utkal quarter described as exceptional now that it runs under long-term PPAs

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 7
“Utkal had an exceptional quarter, now that it operates under long-term PPAs.”

Thermal - KSK Mahanadi: Part of Mahanadi new capacity may be kept for merchant sales; long-term PPAs remain focus

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 8
“If the evening-peak trend continues, with demand rising the way it has been and the same growth drivers in play, we may also look at keeping part of the capacity open for merchant sales.”

Thermal - Utkal: Utkal ran at about 82% PLF in Q2 after outages in Q1

C. Prabhakaran · Chief Financial Officer · Q&A · p. 9
“As you are aware, we had a robust plant performance and we are at about close to 82% of PLF this year this quarter. Wherein we had certain kind of operational issues, outages in the last quarter.”

Demand

Group captive: JSW Group RTC power need expected to more than double to about 7 GW by 2032

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 5
“With JSW Steel planning to expand capacity to up to 80 MTPA, and other Group businesses scaling rapidly, the Group’s RTC power requirement is expected to more than double to around 7 GW by 2032.”

Management sees 5-6% long-term power demand CAGR, possibly conservative

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 3
“These support our view of a 5–6% long-term CAGR in power demand, and the last two quarters suggest that view may prove conservative.”

India power demand grew about 11.1% in Q2 FY27 after 8.3% in Q1

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 3
“Power demand in Q2 FY27 grew about 11.1% year-on-year, building on 8.3% growth in Q1.”

Thermal: States awarded about 17 GW thermal in FY26; further 18 GW under bidding

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 4
“States awarded around 17 GW of long-term thermal capacity at tariffs of about ₹5.4 to ₹6.3 per unit in FY26, and a further 18 GW of thermal tenders are currently under bidding.”

Group captive: Company meets about 3 GW of round-the-clock power demand for JSW Group

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 5
“JSW Energy has long been the energy partner of choice for the JSW Group, meeting around 3 GW of round-the-clock thermal and renewable power demand across Group companies.”

Margins and costs

Merchant: Merchant realisation about Rs 6.9 per unit, about 20% above DAM average

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 4
“Our merchant realisation, however, stood around ₹6.9 per unit which was around 20% higher than the DAM average, driven by the strategic bilateral contracts we have entered into.”

Thermal: Domestic coal shift and job-work deals offset higher imported coal prices

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 4
“Despite this increase, our transition to domestic coal and the implementation of job-work arrangements at imported-coal plants, which shield us from fuel-price volatility, have enabled us to effectively mitigate the impact and maintain cost competitiveness.”

Depreciation up 17% to Rs 943 crore; finance costs up 14% to Rs 1,615 crore

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 7
“depreciation rose 17% to ₹943 crore, and finance costs rose 14% to ₹1,615 crore, in line with the pace of capacity we are adding.”

Thermal: Maruti plant fully domestically fuelled under long-term FSA with SECL

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 6
“Recently acquired Maruti Thermal Plant is also fully domestically fuelled, through a long-term Fuel Supply Agreement with SECL and linkage under the SHAKTI scheme.”

Thermal: API4 coal averaged about US$115 per tonne in Q2 FY27, up about 28% from US$90

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 4
“API4 benchmark coal prices averaged close to US$115 per tonne in Q2 FY27, up around 28% year-on-year from US$90 per tonne.”

Debt and working capital

ICRA and India Ratings affirmed long-term rating at AA, Stable outlook

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 6
“ICRA and India Ratings have affirmed JSW Energy's long-term credit rating at AA with a Stable outlook.”

About a quarter of term debt fixed; nearly 90% of floating debt linked to MCLR

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 7
“Close to a quarter of our term debt is at fixed rates, and nearly 90% of the floating portion is linked to lenders’ internal benchmarks like MCLR, rather than Repo or other market linked instruments like Treasury-bills etc.”

No immediate rise in debt cost seen; possible modest medium-term impact if hikes continue

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 7
“we do not see any immediate rise in debt cost, and may be only a modest impact, in the medium term, if the interest rates hikes continues.”

Debt cost down about 51 bps to 8.28% from about 8.79% a year back

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 7
“our Debt cost has come down significantly by about 51 bps to 8.28%, from about 8.79%, a year back.”

Net debt to TTM EBITDA about 4.94x excluding CWIP debt; cash about Rs 15,700 crore

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 7
“Excluding debt tied to capital work-in-progress, our Net Debt to TTM EBITDA stands at about 4.94 times, down from about 5.2 times in FY26. We hold cash and cash equivalents of about ₹15,700 crore”

Fund raising

Rs 10,150 crore capital unlocked this calendar year for deleveraging

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 6
“the deleveraging we delivered through the ₹10,150 crore capital unlocking in this calendar year.”

Fundraising and JSW Steel share sale added Rs 7,150 crore

C. Prabhakaran · Chief Financial Officer · Q&A · p. 16
“And as you are aware that we did a fundraising and some of the steel shares, which happened, both put together, so we added another ₹7,150 crores.”

Cash accrual and funds raised together about Rs 13,150 crore for equity funding

C. Prabhakaran · Chief Financial Officer · Q&A · p. 16
“So these two put together is about close to ₹13,150 crores. So, our equity funding visibility is ample.”

Acquisitions and new business

Thermal: Maruti Clean Coal & Power acquired in August at EV of Rs 1,410 crore

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 5
“We completed the acquisition of Maruti Clean Coal & Power in August at an enterprise value of ₹1,410 crore. It is EBITDA and PAT accretive from day one and lowers our net leverage.”

Thermal: Maruti: about 195 MW under long-term PPA with Rajasthan, about 64 MW merchant

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 5
“About 195 MW (net) is tied up under a long-term PPA with Rajasthan discoms with around 14 years of residual life, while about 64 MW gives us merchant exposure at a time of strong prices.”

Thermal: Maruti plant generated about Rs 45 crore EBITDA in 55 days of Q2

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 5
“In Q2, this plant generated about ₹45 crore of EBITDA in just 55 days, from our acquisition on August 6th to the end of the quarter.”

Thermal equipment: Toshiba JSW stake raised to 10.7%; GE Power India boiler business deal got NCLT sanction

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 6
“we raised our stake in Toshiba JSW Power Systems to 10.7% in July. The scheme to acquire GE Power India's boiler business, including its Durgapur manufacturing facility, received NCLT sanction on October 1st, and the transaction should close soon.”

Thermal: Company will not bid for West Bengal site-specific thermal tender

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 17
“So, when studied, we found that there are many other more opportunities in the country, suited to our needs. So we are not participating in that.”

Risks

Renewables: Curtailment about 4.8% of H1 generation vs national 5.4%; Q2 revenue impact Rs 59 crore

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 6
“Curtailment across our portfolio stood at about 4.8% of total generation in H1, below the national level curtailment of about 5.4%. In Q2, our curtailed units stood at ~225 MUs with a Revenue impact of Rupees 59 Crores.”

Renewables: About 60% of curtailed capacity to move to permanent GNA by end of Q3 FY27

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 6
“Further, about 60% of our curtailed capacity currently on temporary GNA will move to permanent GNA by the end of Q3 FY27, which should reduce our exposure meaningfully.”

Renewables: Management says capacity plan is insulated from curtailment challenges

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 10
“So I think what we have planned, after evaluating what are the challenges which are coming in, our planning is insulated from any curtailment challenges.”

Renewables: Curtailment described as a very temporary phenomenon for the company

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 10
“For us, this curtailment is a very, very temporary phenomenon.”

Domestic coal stocks at multi-year lows; about 96 plants classified critical in October

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 4
“Coal stocks at power plants fell to multi-year lows, and in October around 96 plants were classified as critical, holding an average of 6–7 days of stock against the normative 19–20 days.”

Other

Q2 net generation up 17% to 17.5 billion units

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 6
“Net generation for Q2 FY27 increased by 17% year-on-year to 17.5 billion units, driven by robust capacity addition and healthy plant performance.”

Q2 revenue Rs 6,658 crore, up 24%; EBITDA Rs 3,907 crore, up 23%

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 7
“revenue for the quarter was ₹6,658 crore, up 24% year-on-year, and EBITDA was ₹3,907 crore, up 23%”

Q2 PAT Rs 1,141 crore, up 38%; attributable PAT Rs 1,056 crore, up 50%

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 7
“Profit After Tax was ₹1,141 crore, up 38% year-on-year, and PAT attributable to shareholders was ₹1,056 crore, up 50% YoY.”

Cash return on net worth about 15%, adjusted for JSW Steel shareholding

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · p. 7
“our cash return on net worth, adjusted for our JSW Steel shareholding, stands at about 15%.”

Merchant: 1.1 BUs sold in the merchant market in the quarter

Sharad Mahendra · Joint Managing Director and Chief Executive Officer · Q&A · p. 11
“It is 1.1 BUs, which we have sold during the quarter, 1.1 BUs.”