Power · NSE: ADANIENSOL
Adani Energy Solutions
Q2 FY27 earnings call · Guided by management
Call held 23 Oct 2026 · Read the filing on NSEFiling
- M.Cap
- ₹1,75,384Cr₹1.75L Cr
- P/E
- 47.3×
- 1Y return
- +43.14%
- From 52W high
- −19.8%
Highlights are read by AI from the company's filing and can contain mistakes. Check the source page linked to each line.
Share price
Results Q2 FY27, as filed · consolidated · ₹ Cr
| Q2 FY27 | Q2 FY26 | YoY | Q1 FY27 | QoQ | |
|---|---|---|---|---|---|
| Revenue | 10,076 | 6,596 | +52.8% | 9,711 | +3.8% |
| EBITDA | 3,101 | 2,289 | +35.5% | 3,008 | +3.1% |
| EBITDA margin | 30.8% | 34.7% | -393 bps | 31.0% | -21 bps |
| One-off items | — | — | — | 29 | — |
| PBTProfit before tax | 1,484 | 1,079 | +37.5% | 1,441 | +3.0% |
| Net profit | 1,323 | 534 | +147.7% | 1,149 | +15.1% |
| EPS (₹) | 11.01 | 6.19 | +77.9% | 9.57 | +15.0% |
From the company's own results filing on NSE. Net profit is the owners' share. Growth and the dotted lines are worked out from the filed figures.
Guidance
Transmission: No need seen now to revise transmission capex guidance
Kandarp Patel · Chief Executive Officer · Q&A · p. 9
Transmission: No need seen now to revise transmission capex guidance
“So we do not see a requirement currently as of now to revise the capex guideline, and we hope that we will be able to do it in next 6 months of this year.”
More figures from the call
“So the capitalization also would be of the order of INR8,000 crores to INR9,000 crore.”
“Capitalization would be about, give me a minute, that will also be of the order of INR10,000 crores.”
“But on an overall basis, it would be of the order of 3,500 million units per quarter.”
“So asset will grow almost 1.3x, 1.4x from what we have today in next 5 years.”
In short
- 01Transmission capex for FY27 is guided at about Rs 14,000 crore, with Rs 8,000-9,000 crore in the second half.
- 02Transmission capex of Rs 18,000-19,000 crore is expected in FY28; capitalisation about Rs 8,000-9,000 crore in FY27 and about Rs 10,000 crore in FY28.
- 03Management does not see a need now to revise the transmission capex guidance.
- 04The company has more than Rs 1,00,000 crore of capex locked in, to be delivered over 4 to 5 years; asset base is about Rs 83,000 crore.
- 05Smart meter installations planned at about 80 to 90 lakh this year; first-half deployment was below expectation.
- 06Energy Solutions aims for 7,000-8,000 MW of tie-ups over 3 to 4 years; long-term PPA margins expected at Rs 0.80-1 per unit.
- 07The 2,500 MW MSEDCL contract starts supply from end of February in phases; the 750 MW AEML PPA is expected to be signed in 3 to 4 weeks.
- 08Intellismart deal awaits CCI approval and is expected to close in about one month.
Capex
Energy Solutions: Sourcing for MSEDCL 2,500 MW contract about 50% covered
Raj Kumar Jain · Business Head · Q&A · p. 8
Energy Solutions: Sourcing for MSEDCL 2,500 MW contract about 50% covered
“So I would say this way that within the Maharashtra one, 2,500 megawatts, we have broadly covered 50% right now based on our sourcing.”
Transmission: Navinal project may finish this year or spill into next year's first half
Kandarp Patel · Chief Executive Officer · Q&A · p. 6
Transmission: Navinal project may finish this year or spill into next year's first half
“We might complete the Navinal project in the current year, or maybe it may spill over in the next year first half.”
Transmission: Mahan phase 1 to be commissioned; phase 2 in next year's first quarter
Kandarp Patel · Chief Executive Officer · Q&A · p. 7
Transmission: Mahan phase 1 to be commissioned; phase 2 in next year's first quarter
“And in Mahan as well, phase 1 will get commissioned, the phase 2 will be in next year first quarter.”
Transmission: All H2 transmission contracts awarded and contractors mobilised
Kandarp Patel · Chief Executive Officer · Q&A · p. 5
Transmission: All H2 transmission contracts awarded and contractors mobilised
“All the contracts has been awarded, teams has been mobilized, contractor has been mobilized, and you will see a lot of execution activity on the ground scaling up in the second half.”
Transmission: WRSR transmission project expected to be commissioned this year
Kandarp Patel · Chief Executive Officer · Q&A · p. 6
Transmission: WRSR transmission project expected to be commissioned this year
“The other project that we expect to commission would be WRSR in this year, and probably we will complete.”
Capacity
Energy Solutions: Supply tie-up of 4 GW renewables and 3.5 GW base capacity
Kandarp Patel · Chief Executive Officer · p. 4
Energy Solutions: Supply tie-up of 4 GW renewables and 3.5 GW base capacity
“And we already have a tie-up of 4 gigawatt of renewables and 3.5 gigawatt of base capacity.”
Transmission: One element of Khavda phase 4, Khavda-Bhuj, commissioned
Kandarp Patel · Chief Executive Officer · Q&A · p. 6
Transmission: One element of Khavda phase 4, Khavda-Bhuj, commissioned
“Mahesh, we recently commissioned one element of phase 4, Khavda-Bhuj recently.”
Order book
Transmission: Transmission order book about Rs 87,000 crore after two new projects
Kandarp Patel · Chief Executive Officer · p. 3
Transmission: Transmission order book about Rs 87,000 crore after two new projects
“And with these two projects, our order book remains at about INR87,000 crores.”
Smart Metering: 14.8 million smart meters delivered, about 60% of order book; rest in 12 to 14 months
Kandarp Patel · Chief Executive Officer · p. 4
Smart Metering: 14.8 million smart meters delivered, about 60% of order book; rest in 12 to 14 months
“Smart Metering, we have now delivered about 14.8 million meters so far. And around 60 percentage of our order book, that we have delivered and balance portion, we wish to complete in another 12 to 14-month time.”
Transmission: Satara and Pendurthi, won last quarter, are both interstate projects
Kandarp Patel · Chief Executive Officer · Q&A · p. 14
Transmission: Satara and Pendurthi, won last quarter, are both interstate projects
“So both the projects that we have won last quarter, one is Satara as well as second is Pendurthi. Both are interstate projects.”
Transmission: Satara project serves PSP projects; Pendurthi serves Vizag data centers
Kandarp Patel · Chief Executive Officer · p. 3
Transmission: Satara project serves PSP projects; Pendurthi serves Vizag data centers
“Satara is important for development of PSP projects and Pendurthi is for data centers that is coming up in Vizag region.”
Segments
Distribution: Mumbai distribution losses down to 4.29% in H1; consumption up over 10%
Kandarp Patel · Chief Executive Officer · p. 4
Distribution: Mumbai distribution losses down to 4.29% in H1; consumption up over 10%
“Our Distribution losses in Mumbai has reduced further to 4.29 percentage in the first half. And this despite the fact that consumption has also increased by more than 10 percentage.”
C&I and Energy Solutions platform: Energy Solutions platform Q2 revenue over Rs 2,000 crore, EBITDA over Rs 800 crore
Kandarp Patel · Chief Executive Officer · p. 4
C&I and Energy Solutions platform: Energy Solutions platform Q2 revenue over Rs 2,000 crore, EBITDA over Rs 800 crore
“During this quarter, the platform delivered revenue of over INR2,000 crores and EBITDA of over INR800 crores.”
Smart Metering: Smart meter pace in Bihar and Maharashtra expected to rise
Kandarp Patel · Chief Executive Officer · Q&A · p. 5
Smart Metering: Smart meter pace in Bihar and Maharashtra expected to rise
“in Bihar and Maharashtra where the pace was low, we expect that to increase significantly.”
Energy Solutions: Energy Solutions to tie up capacity long term on both sides for stable revenue
Kandarp Patel · Chief Executive Officer · p. 11
Energy Solutions: Energy Solutions to tie up capacity long term on both sides for stable revenue
“We will continue to tie up capacity on both sides on a long-term basis, so that we have stability in revenue as well as profitability.”
Energy Solutions: MSEDCL long-term PPA to start operating from last quarter of this year
Kandarp Patel · Chief Executive Officer · p. 6
Energy Solutions: MSEDCL long-term PPA to start operating from last quarter of this year
“And you must have seen that we have done this long-term PPA with MSEDCL, which will start operating from last quarter of this year.”
Demand
Energy Solutions: Consumer PPAs total 3,250 MW; advanced talks with data center customers
Raj Kumar Jain · Business Head · Q&A · p. 8
Energy Solutions: Consumer PPAs total 3,250 MW; advanced talks with data center customers
“So one, obviously, you have 2,500 megawatts of the MSEDCL PPA, 750 megawatt of AEML, so that's 3,250 megawatts. We are targeting multiple data center customers. We are in advanced discussions with them.”
Energy Solutions: Close to 400 MW of smaller C&I clients
Raj Kumar Jain · Business Head · Q&A · p. 8
Energy Solutions: Close to 400 MW of smaller C&I clients
“we also have close to 400 megawatts of C&I clients, which are smaller ones”
Smart Metering: Smart meter auctions under way; company bidding to grow portfolio
Raj Kumar Jain · Business Head · Q&A · p. 10
Smart Metering: Smart meter auctions under way; company bidding to grow portfolio
“There are already current auctions, which are there in market. We are participating, and we believe that the portfolio can be ramp up because the market is seeing the benefits of it coming in, and we are fully positioned to actually tap that opportunity.”
Transmission: Country transmission tender pipeline around Rs 1,40,000 crore
Raj Kumar Jain · Business Head · Q&A · p. 14
Transmission: Country transmission tender pipeline around Rs 1,40,000 crore
“And right now, see, I think the tender pipeline itself at the country level is around INR140,000 crores.”
Distribution: Mumbai consumption up about 11% to 12% this year
Kandarp Patel · Chief Executive Officer · p. 14
Distribution: Mumbai consumption up about 11% to 12% this year
“like this year, we see consumption increase in the city of Mumbai of the order of 11 percentage to 12 percentage.”
Margins and costs
Energy Solutions: Average trading realisation about Rs 5.75; exchange sales earn Rs 0.02-0.03 per unit
Ashok Jagetiya · Chief Financial Officer · Q&A · p. 8
Energy Solutions: Average trading realisation about Rs 5.75; exchange sales earn Rs 0.02-0.03 per unit
“See, the average realization as far as trading is concerned is about INR5.75. And what we sell on exchange on behalf of others, we get about INR0.02 to INR0.03 per unit.”
Energy Solutions: Company expects to keep healthy margins across diversified consumer base
Raj Kumar Jain · Business Head · Q&A · p. 10
Energy Solutions: Company expects to keep healthy margins across diversified consumer base
“But we believe that we will continue to maintain healthy margins in our businesses across the diversified consumer base, and that's what you would see.”
Energy Solutions: Margin on position-taking sales about Rs 1.70 to Rs 2
Kandarp Patel · Chief Executive Officer · Q&A · p. 15
Energy Solutions: Margin on position-taking sales about Rs 1.70 to Rs 2
“So margin on the -- of the order of INR1.70 to INR2.”
Energy Solutions: Very good EBITDA margin expected as volumes and PPAs come in
Raj Kumar Jain · Business Head · Q&A · p. 11
Energy Solutions: Very good EBITDA margin expected as volumes and PPAs come in
“So with volumes picking up and all of the PPAs coming in, we expect to maintain a very good EBITDA margin in this business.”
Energy Solutions: Market conditions lifted margins before long-term supply starts
Kandarp Patel · Chief Executive Officer · Q&A · p. 6
Energy Solutions: Market conditions lifted margins before long-term supply starts
“And we were fortunate enough that between this period where we start our long-term supply, the market was good and we have been able to earn a good margin.”
Debt and working capital
ECB about 10% of overall debt of Rs 51,000 crore
Ashok Jagetiya · Chief Financial Officer · Q&A · p. 15
ECB about 10% of overall debt of Rs 51,000 crore
“On the borrowing side, ECB is around 10%. On the overall debt of INR51,000 crores, 10% is from the ECB.”
75% to 80% of debt on fixed coupon
Ashok Jagetiya · Chief Financial Officer · Q&A · p. 15
75% to 80% of debt on fixed coupon
“So 75% to 80% of our debt portfolio is on fixed coupon basis.”
Most debt fixed rate or hedged; little FX or rate volatility expected
Kandarp Patel · Chief Executive Officer · p. 4
Most debt fixed rate or hedged; little FX or rate volatility expected
“On our funding and balance sheet side, a significant portion of our debt is also the fixed rate or hedged appropriately. So we don't expect much of the volatility due to foreign exchange or interest rate realization in our P&L or balance sheet.”
Acquisitions and new business
Energy Solutions: 2,500 MW RE-RTC contract signed with MSEDCL
Kandarp Patel · Chief Executive Officer · p. 4
Energy Solutions: 2,500 MW RE-RTC contract signed with MSEDCL
“We executed a 2,500-megawatt RE-RTC contract with MSEDCL.”
Smart Metering: Intellismart deal to close after CCI approval, expected in about one month
Kandarp Patel · Chief Executive Officer · Q&A · p. 5
Smart Metering: Intellismart deal to close after CCI approval, expected in about one month
“And once we have the CCI approval, we will complete the transaction immediately. So we expect that will happen in next one month time.”
Energy Solutions: Another PPA with AEML to be signed; regulatory approval received
Kandarp Patel · Chief Executive Officer · p. 6
Energy Solutions: Another PPA with AEML to be signed; regulatory approval received
“We will be doing another PPA with AEML, where regulatory approval has already been achieved, so we will be doing that PPA.”
Energy Solutions: 750 MW AEML PPA approved by regulator; signing expected in 3 to 4 weeks
Raj Kumar Jain · Business Head · Q&A · p. 13
Energy Solutions: 750 MW AEML PPA approved by regulator; signing expected in 3 to 4 weeks
“As far as 750 megawatts is concerned, that's already approved by the regulator. All process already done. We are in the process of executing that, expect that to happen over the course of next 3 to 4 weeks.”
Smart Metering: Smart metering acquisition opportunity possible besides bidding
Kandarp Patel · Chief Executive Officer · Q&A · p. 10
Smart Metering: Smart metering acquisition opportunity possible besides bidding
“And there could also be an opportunity of acquisition in the market on top of what we get here through bidding.”
One-offs
Transmission: MAT assets of about Rs 1,500 crore recognised in MEGPTCL and ATIL on new tax regime
Ashok Jagetiya · Chief Financial Officer · Q&A · p. 7
Transmission: MAT assets of about Rs 1,500 crore recognised in MEGPTCL and ATIL on new tax regime
“See, there are two companies, MEGPTCL and ATIL, where we have decided to go to the new tax regime and recognize the past paid MAT assets in the books of account which are close to around INR1,500 crores.”
MAT asset recognition has no P&L impact due to matching recoverable liability
Ashok Jagetiya · Chief Financial Officer · Q&A · p. 7
MAT asset recognition has no P&L impact due to matching recoverable liability
“Since these are Section 62 assets, and therefore corresponding adjustable recoverable liability has also been created and to that extent, there is no impact on P&L.”
Risks
Smart Metering: H1 smart meter deployment was lower than the company expected
Kandarp Patel · Chief Executive Officer · Q&A · p. 5
Smart Metering: H1 smart meter deployment was lower than the company expected
“Yes, obviously, the deployment in the first half was lower than even our expectation and those reasons were mainly extraneous”
Transmission: Halvad line held up by right-of-way problem; resolution expected soon
Kandarp Patel · Chief Executive Officer · Q&A · p. 6
Transmission: Halvad line held up by right-of-way problem; resolution expected soon
“Halvad is stacked up because of the ROW problem. And we expect resolution very soon.”
Transmission: WRSR using drones for stringing to avoid ROW issue; completion expected this year
Kandarp Patel · Chief Executive Officer · Q&A · p. 9
Transmission: WRSR using drones for stringing to avoid ROW issue; completion expected this year
“We have started utilizing drone to avoid ROW problem for stringing. So we expect that to complete in this year only.”
Energy Solutions: Curtailment: company liable only once power is scheduled
Kandarp Patel · Chief Executive Officer · Q&A · p. 17
Energy Solutions: Curtailment: company liable only once power is scheduled
“Currently, they have not been able to schedule corresponding to the curtailment that is being enforced. So our responsibility starts the moment power is scheduled.”
Smart Metering: Customer resistance slowed smart meter rollout; education campaign stepped up
Kandarp Patel · Chief Executive Officer · Q&A · p. 5
Smart Metering: Customer resistance slowed smart meter rollout; education campaign stepped up
“those reasons are obviously resistance from people for a smart meter, where we have now ramped up our campaign to educate those customers.”
Other
Q2 total income up over 50%, EBITDA up close to 67%, PAT up 145%
Kandarp Patel · Chief Executive Officer · p. 4
Q2 total income up over 50%, EBITDA up close to 67%, PAT up 145%
“Financially as well, we delivered another strong quarter with total income growing over 50 percentage. EBITDA also increasing close to 67 percentage and PAT growing 145 percentage.”
Energy Solutions: No tie-up with Adani Power; about 650-700 MW of supply from third parties
Kandarp Patel · Chief Executive Officer · Q&A · p. 15
Energy Solutions: No tie-up with Adani Power; about 650-700 MW of supply from third parties
“So there is no tie-up with Adani Power as of now. But out of the total capacity, around 700 megawatts is from third party as well, 650 megawatts.”
Ranked number one globally in S&P Global Electric Utility category, 90 out of 100
Kandarp Patel · Chief Executive Officer · p. 4
Ranked number one globally in S&P Global Electric Utility category, 90 out of 100
“now in S&P Global Electric Utility category, we are number one globally, getting 90 out of 100 rank, where industry average is about 40”
Energy Solutions: Supply sourcing to include thermal, PSP, renewables and BESS
Raj Kumar Jain · Business Head · Q&A · p. 8
Energy Solutions: Supply sourcing to include thermal, PSP, renewables and BESS
“So it will be having all kinds of sources, including thermal, PSP, renewables, BESS and whatnot.”
Energy Solutions: Any Adani Green capacity tie-ups to be on market benchmarks
Raj Kumar Jain · Business Head · Q&A · p. 11
Energy Solutions: Any Adani Green capacity tie-ups to be on market benchmarks
“So obviously, we connect with them as well for these capacities, and you would see some of those happening in the near future, but purely on the market benchmarks, where the value is available for both the entities, if at all those transactions happen.”
Sources
- Earnings call transcript, Q2 FY27 Filed 30 Oct 2026 · 17 pages
Management's own statements, quoted from its NSE filings. This page was read by AI and can contain mistakes: check the source pages before relying on any figure. No forecast or opinion of ours. Not investment advice.